Construction of Time – Cost Model for Building Projects in Vietnam

Bromilow’s time-cost (BTC) relationship was examined for building projects in Vietnam using actual construction time and total construction cost. Data set was collected from 77 historical building construction projects completed between 1999 and 2005 which were adjusted by consumer price index (CPI)...

Full description

Saved in:
Bibliographic Details
Published in한국건설관리학회 논문집, 10(3) pp. 130 - 138
Main Authors Long Le-Hoai, Young Dai Lee, Jeong Wook Cho
Format Journal Article
LanguageEnglish
Published 한국건설관리학회 01.05.2009
Subjects
Online AccessGet full text
ISSN2005-6095
2465-9703

Cover

More Information
Summary:Bromilow’s time-cost (BTC) relationship was examined for building projects in Vietnam using actual construction time and total construction cost. Data set was collected from 77 historical building construction projects completed between 1999 and 2005 which were adjusted by consumer price index (CPI) to 2000 price. Time-cost equations were specified respected to two sectors, public and private, in Vietnamese construction industry and all cases. It is shown that a public funded building project has the longer construction duration than a similar budget private funded project. The resulting models are statistically significant. The adjusted R-square coefficients of all cases, public and private projects models are respectively 0.403, 0.436 and 0.377 mean that the BTC regression lines moderately fit the data set. KCI Citation Count: 3