METHOD OF CONSTRUCTING UPPER STRUCTURE OF BRIDGE USING PSC GIRDER

The present invention relates to a method of constructing a superstructure of a bridge for suppressing deformation during manufacturing site stacking time of prestressed concrete girders. The method of constructing a superstructure of a bridge comprises: a girder arranging step of arranging a plural...

Full description

Saved in:
Bibliographic Details
Main Authors PYUN MYUNG CHEOL, PARR, KI WON
Format Patent
LanguageEnglish
Korean
Published 31.12.2019
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:The present invention relates to a method of constructing a superstructure of a bridge for suppressing deformation during manufacturing site stacking time of prestressed concrete girders. The method of constructing a superstructure of a bridge comprises: a girder arranging step of arranging a plurality of concrete girders including a first concrete girder and second concrete laterally adjacent to each other; a temporary steel pipe cross beam installing step of laterally connecting concrete girders arranged in two or more rows by a temporary steel pipe cross beam to restrict lateral deformation of the concrete girders; and a girder stacking step of stacking the concrete girders until lifting the concrete girders for bridge construction in a state where the temporary steel pipe cross beam installing step has been performed. Accordingly, the present invention manufactures concrete girders for a bridge and connects a temporary steel pipe cross beam between the manufactured concrete girders in the lateral direction to restrict lateral displacement of the concrete girders by the temporary steel pipe cross beam during stacking time before lifting the concrete girders to suppress lateral changes of the concrete girders during the stacking time. 본 발명은 프리스트레스트 콘크리트 거더의 제작장 적치 기간 중 변형을 억제하는 교량 상부 구조의 시공 방법에 관한 것으로, 횡방향으로 인접한 제1콘크리트 거더와 제2콘크리트를 포함하는 다수의 콘크리트 거더를 배치하는 거더 배치 단계와; 2열 이상으로 배열된 콘크리트 거더를 임시강관 가로보로 횡방향으로 연결하여 상기 콘크리트 거더의 횡방향으로의 변형을 구속하는 임시강관가로보 설치단계와; 상기 임시강관가로보 설치단계가 행해진 상태에서 상기 콘크리트 거더를 교량의 시공을 위한 인상 시까지 적치시키는 거더 적치 단계를; 포함하는 교량 상부 구조의 시공 방법을 제공한다. 이를 통해, 본 발명은, 교량용 콘크리트 거더를 제작하고 인상되기 이전의 적치 기간 동안에, 제작된 콘크리트 거더의 횡방향 사이에 임시강관 가로보를 연결하여 콘크리트 거더의 횡방향으로의 변위를 임시강관 가로보에 의해 구속시킴으로써, 적치 기간 동안에 콘크리트 거더의 횡변위가 변동하는 것을 억제하는 효과를 얻을 수 있다.
Bibliography:Application Number: KR20180138567