FLOOR CONSTRUCTION METHOD AND FLOOR STRUCTURE

To provide means to cut man hour of floor construction works to reduce the labor for floor construction.SOLUTION: A floor construction method in this invention comprises: a process, which erects, on a rising part R of a foundation B of a building 1, a sleeper 12 of an underfloor unit 20 that integra...

Full description

Saved in:
Bibliographic Details
Main Authors ASANO SHOHEI, TANAKA SHUSUI, FUJIYAMA SEIJI, SHIMADA TAKEHIKO, BABA MINEO, KURODA HIROSHI
Format Patent
LanguageEnglish
Japanese
Published 17.10.2019
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:To provide means to cut man hour of floor construction works to reduce the labor for floor construction.SOLUTION: A floor construction method in this invention comprises: a process, which erects, on a rising part R of a foundation B of a building 1, a sleeper 12 of an underfloor unit 20 that integrates the sleeper 12 supporting a floor panel 11 constituting a floor of the building 1 and a strut 13 supporting the sleeper 12, to locate the underfloor unit 20; a process, which forms a dirt floor FL by pouring concrete up to a level higher than the bottom end 15ca of the strut 13 after locating the underfloor unit 20; a process, in which, after forming the dirt floor FL, a leg member 16 that is provided on the strut 13 and vertically movable against the strut 13 is moved downwards to be anchored to the dirt floor FL; a process which places the floor panel 11 on the sleeper 12 in such a way that the top part of the strut 13 is exposed through the floor panel 11; and a process, which vertically alters the attachment position of the strut 13 against the sleeper 12 by working the top part 17 of a screw provided at the top of the strut 13 put together with the sleeper 12 in order to adjust the vertical position of the sleeper 12.SELECTED DRAWING: Figure 1 【課題】床施工の工数を削減し、床施工に係る労力を軽減する。【解決手段】床施工方法は、建物1の床を構成する床パネル11を支持する大引12と、大引12を支持する束13とを一体化した床下ユニット20の大引12を建物1の基礎Bの立ち上がり部Rに架設して、床下ユニット20を配置する工程と、床下ユニット20を配置した後に、束13の下端部15caより高い位置までコンクリートを打設して土間FLを形成する工程と、土間FLを形成した後に、束13に設けられ、束13に対して上下に移動可能な脚部材16を下方に移動させて土間FLに定着させる工程と、床パネル11から束13の上部が露出するように、大引12の上に床パネル11を配置する工程と、大引12の上下位置を調整するために、大引12に組み付けられた束13の上部に設けられたネジ頂部17を操作して、大引12に対する束13の組み付け位置を上下方向において変更する工程を含む。【選択図】図1
Bibliography:Application Number: JP20180069521