Method for judging that 110kV main transformer does not meet N-1 in consideration of 10kV transfer

The invention relates to the field of power systems, in particular to a method for judging whether a 110kV main transformer does not meet N-1 in consideration of 10kV transfer, which comprises the following steps of: checking whether a 110kV transformer substation meets the requirement of short-time...

Full description

Saved in:
Bibliographic Details
Main Authors LIU HENGWEI, WU GUOYUE, LIANG YI, LIN ZIHAN, GAO YANNA, CHEN LIPING, DONG HONG, HU LIUJUN, ZHU ZHIFANG, GUO ZIXUAN
Format Patent
LanguageChinese
English
Published 18.08.2023
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:The invention relates to the field of power systems, in particular to a method for judging whether a 110kV main transformer does not meet N-1 in consideration of 10kV transfer, which comprises the following steps of: checking whether a 110kV transformer substation meets the requirement of short-time overload capacity of the main transformer after the N-1 of the main transformer, if the 110kV transformer substation meets the requirement of short-time overload capacity of the main transformer after the N-1 of the main transformer, determining that the transformer substation meets N-1, and if the 110kV transformer substation meets the requirement of short-time overload capacity of the main transformer after the N-1 of the main transformer, determining that the transformer substation meets N-1, otherwise, determining that the transformer if the 110kV transformer substation does not meet the requirement of the short-time overload capacity of the main transformer after the main transformer is N-1, checking the 10kV
Bibliography:Application Number: CN202310476710