Rapid excavation method for rock-anchored beam of underground powerhouse
The invention discloses a rapid excavation method for an underground powerhouse rock-anchored beam. The excavation of the underground powerhouse is sequentially divided into first layer excavation, small flat layer excavation, middle groove broaching, rock bench protection layer excavation and rock-...
Saved in:
Main Authors | , , , , , , , , , , , |
---|---|
Format | Patent |
Language | Chinese English |
Published |
18.08.2023
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | The invention discloses a rapid excavation method for an underground powerhouse rock-anchored beam. The excavation of the underground powerhouse is sequentially divided into first layer excavation, small flat layer excavation, middle groove broaching, rock bench protection layer excavation and rock-anchored beam slope rock bench excavation according to the section. Comprising the steps that after a small flat layer above a rock bench is excavated to an upper straight wall, a buffer crack is formed between a rock bench protection layer rock mass and a middle broaching groove rock mass through presplitting blasting, then upper straight wall smooth blasting drilling, middle broaching groove bench blasting excavation and rock bench protection layer excavation are sequentially carried out, and finally inclined blasting hole drilling is carried out on an inclined rock bench. And smooth blasting is conducted on the upper straight wall and the slope blasting holes simultaneously, and slope rock bench excavation is co |
---|---|
Bibliography: | Application Number: CN202310759034 |