Hard granite stratum variable cross-section pile foundation hole forming method and pouring method

The invention discloses a hard granite stratum variable cross-section pile foundation hole forming method and pouring method.The hole forming method comprises the following steps that S1, a pile foundation operation platform is erected, and a pile casing positioning and guiding device is installed o...

Full description

Saved in:
Bibliographic Details
Main Authors LU HAIJUN, LI MINHENG, ZHOU MIAO, SHA HANGYU, LIN GUANGDONG, CHEN ZHONGWEN, LUO YU, LIU JIAXING, ZHAN CHUANZE, REN PANFENG, LIU CHEN, LI YUANXING
Format Patent
LanguageChinese
English
Published 15.08.2023
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:The invention discloses a hard granite stratum variable cross-section pile foundation hole forming method and pouring method.The hole forming method comprises the following steps that S1, a pile foundation operation platform is erected, and a pile casing positioning and guiding device is installed on the pile foundation operation platform so that the axial deviation and verticality construction quality of a pile foundation in water can be improved; s2, the pile casing is lowered down along the pile casing positioning and guiding device, and the pile casing is vibrated and buried into a rock stratum in water through a vibration device; s3, a rotary drilling rig is in place, a rotary drilling rock-entering pile forming mode is adopted, a multi-drill-bit combined sleeve drill extends into the pile casing, and drilling is conducted on the rock stratum step by step; and drilling construction of the lower portion of the variable-cross-section pile foundation is completed until the drill bit drills to the designed b
Bibliography:Application Number: CN202310408909