River closure construction method for river-crossing cast-in-place bridge support foundation

The invention discloses a river-crossing cast-in-place bridge support foundation river channel closure construction method which comprises the following steps: determining closure design flow and closure conditions according to average flow of a river channel in unit time; a construction shortcut is...

Full description

Saved in:
Bibliographic Details
Main Authors PAN JIYING, LIU YAN, LI LANJU, AN YONG, ZHOU BINGQIU
Format Patent
LanguageChinese
English
Published 02.05.2023
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:The invention discloses a river-crossing cast-in-place bridge support foundation river channel closure construction method which comprises the following steps: determining closure design flow and closure conditions according to average flow of a river channel in unit time; a construction shortcut is arranged, and river channel desilting and rock ballast embankment are conducted; stone ballast occupation is carried out behind the embankment; in the occupation construction period, the flow guide pipes are buried in the mode of excavation after filling; dressed stone closure is carried out at the closure gap of the river channel; and after closure is completed, backfilling and compacting are conducted to form a cushion layer, and river channel closure construction is completed. According to the scheme, the project construction cost can be saved; meanwhile, after the support is dismantled, the filling slag can be used as abutment back filler, is recycled, is material-saving and environment-friendly, and conforms
Bibliography:Application Number: CN202211681364