Protective dismantling construction method for basement pile foundation adjacent to existing subway line

The invention provides a protective dismantling construction method for a pile foundation of a basement adjacent to an existing subway line. The protective dismantling construction method comprises the following steps that the surface of the basement is cleaned, and a construction hoisting hole is f...

Full description

Saved in:
Bibliographic Details
Main Authors LIU ZIYANG, WANG JIE, DU YAO, JIN PING, WANG SHENGTAO, ZHAO GAOFENG, DENG NENGWEI, ZHAO RAN, CHEN TAO, LI RAN, WANG YANG, WU JIALIN, DU HONGBO, FANG ZHIHAI, DENG XIFEI, ZHANG GUANGHUI
Format Patent
LanguageChinese
English
Published 30.08.2022
Subjects
Online AccessGet full text

Cover

Loading…
Abstract The invention provides a protective dismantling construction method for a pile foundation of a basement adjacent to an existing subway line. The protective dismantling construction method comprises the following steps that the surface of the basement is cleaned, and a construction hoisting hole is formed; constructing a retaining wall at the junction position of the underground structure to be dismantled and the non-dismantling side, and meanwhile, constructing a buttress wall on the side wall of the basement to be dismantled; filling an underground structure cavity with backfill soil, and refilling water to ensure balance of underground water levels inside and outside the basement; the basement top plate is dismantled through wire saw cutting; hardening the area above the basement; a bottom plate and a bearing platform of the basement are broken and removed through a full-rotation full-casing drilling machine; the pile foundation is pulled out; and plain concrete backfilling is carried out. The method is use
AbstractList The invention provides a protective dismantling construction method for a pile foundation of a basement adjacent to an existing subway line. The protective dismantling construction method comprises the following steps that the surface of the basement is cleaned, and a construction hoisting hole is formed; constructing a retaining wall at the junction position of the underground structure to be dismantled and the non-dismantling side, and meanwhile, constructing a buttress wall on the side wall of the basement to be dismantled; filling an underground structure cavity with backfill soil, and refilling water to ensure balance of underground water levels inside and outside the basement; the basement top plate is dismantled through wire saw cutting; hardening the area above the basement; a bottom plate and a bearing platform of the basement are broken and removed through a full-rotation full-casing drilling machine; the pile foundation is pulled out; and plain concrete backfilling is carried out. The method is use
Author ZHANG GUANGHUI
DENG NENGWEI
JIN PING
WANG JIE
ZHAO RAN
LIU ZIYANG
ZHAO GAOFENG
WU JIALIN
DENG XIFEI
DU HONGBO
FANG ZHIHAI
WANG YANG
LI RAN
CHEN TAO
WANG SHENGTAO
DU YAO
Author_xml – fullname: LIU ZIYANG
– fullname: WANG JIE
– fullname: DU YAO
– fullname: JIN PING
– fullname: WANG SHENGTAO
– fullname: ZHAO GAOFENG
– fullname: DENG NENGWEI
– fullname: ZHAO RAN
– fullname: CHEN TAO
– fullname: LI RAN
– fullname: WANG YANG
– fullname: WU JIALIN
– fullname: DU HONGBO
– fullname: FANG ZHIHAI
– fullname: DENG XIFEI
– fullname: ZHANG GUANGHUI
BookMark eNqNjDsOglAQRV-hhb89jAuwIBgSS0M0VsbCngy8QZ6BGcIMfnYvGBdgdZN7zz1zN2Fhmrnq0olRYeFB4IM2yFYHvkEhrNb1wyAMDVklHkrpIEelhtigDTUNTc8evwz6OxbjYAL0CmqjRfv8iW8YjLR00xJrpdUvF259PFzT04ZayUjb8UyWpeco2u6SKI6TffwP8wESO0M-
ContentType Patent
DBID EVB
DatabaseName esp@cenet
DatabaseTitleList
Database_xml – sequence: 1
  dbid: EVB
  name: esp@cenet
  url: http://worldwide.espacenet.com/singleLineSearch?locale=en_EP
  sourceTypes: Open Access Repository
DeliveryMethod fulltext_linktorsrc
Discipline Medicine
Chemistry
Sciences
DocumentTitleAlternate 一种紧邻既有地铁线地下室桩基保护性拆除施工方法
ExternalDocumentID CN114961336A
GroupedDBID EVB
ID FETCH-epo_espacenet_CN114961336A3
IEDL.DBID EVB
IngestDate Fri Jul 19 14:18:52 EDT 2024
IsOpenAccess true
IsPeerReviewed false
IsScholarly false
Language Chinese
English
LinkModel DirectLink
MergedId FETCHMERGED-epo_espacenet_CN114961336A3
Notes Application Number: CN202210796491
OpenAccessLink https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20220830&DB=EPODOC&CC=CN&NR=114961336A
ParticipantIDs epo_espacenet_CN114961336A
PublicationCentury 2000
PublicationDate 20220830
PublicationDateYYYYMMDD 2022-08-30
PublicationDate_xml – month: 08
  year: 2022
  text: 20220830
  day: 30
PublicationDecade 2020
PublicationYear 2022
RelatedCompanies CHINA TIESIJU CIVIL ENGINEERING GROUP CO., LTD
RelatedCompanies_xml – name: CHINA TIESIJU CIVIL ENGINEERING GROUP CO., LTD
Score 3.5513463
Snippet The invention provides a protective dismantling construction method for a pile foundation of a basement adjacent to an existing subway line. The protective...
SourceID epo
SourceType Open Access Repository
SubjectTerms BUILDING
BUILDING IMPLEMENTS OR OTHER BUILDING AIDS, OR THEIRUSE
CEILINGS
EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FLOORS
FORMS
FOUNDATIONS
GENERAL BUILDING CONSTRUCTIONS
HANDLING BUILDING MATERIALS ON THE SITE
HYDRAULIC ENGINEERING
INSULATION OR OTHER PROTECTION OF BUILDINGS
REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTINGBUILDINGS
ROOFS
SCAFFOLDING
SHUTTERING
SOIL SHIFTING
UNDERGROUND OR UNDERWATER STRUCTURES
WALLS, e.g. PARTITIONS
Title Protective dismantling construction method for basement pile foundation adjacent to existing subway line
URI https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20220830&DB=EPODOC&locale=&CC=CN&NR=114961336A
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV1NS8NAEB1qFfWmVdH6wQiSW3DbpLE9BLGbhiI0DVKlt5LdbGkLNoVEiv56Z7et9aK3sIElM5u38_Zj3gDcpUq5op4wuyEJTa4rpC3oX7KZqsmx16w1lDlo70Ve99V9HjaGJZhtcmGMTujSiCMSoiThvTDz9WK7iRWYu5X5vZhSU_YYDvzAWq-O63ViFMwK2n4n7gd9bnHu88iKXnyi_S2KXI73tAO7mkZrnf3OW1tnpSx-h5TwCPZi6m1eHEPpa1KBA76pvFaB_d76wJse19jLT2ASryQVaHrCdJq_k0t0KjnKbCsCi6uC0EhMFHV80lt_uCDgU8umfBIm6UybXGCRoRbC1BefMf8Qy-QTNek8hduwM-Bdmz559OOfEY-21jlnUJ5nc3UOSOByaPmmUiZpPFos8VTzQaRjJjxiRcq9gOrf_VT_e3kJh9rXZmuVXUGZjFTXFJsLcWOc-g1KZJZ0
link.rule.ids 230,309,786,891,25594,76903
linkProvider European Patent Office
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV3fT8IwEL4gGvFNUYP4qyZmb4tljAEPi5EOgsoGMdPwtqxbCZDISDZD9K_3WsD5om9LlzS7677ed9feHcBtLITJjZDqjQjRZJo80jn-SzoVtWhitWoNoQ7aXc_qv5pP48a4APNtLoyqE7pSxRERURHiPVP79TIPYjnqbmV6x2c4lNz3fNvRNt6xYSCjoJrTsbujoTNkGmM28zTvxUba30bLVbcedmC3iS6hcpXeOjIrZfnbpPQOYW-Esy2yIyh8TctQYtvOa2XYdzcH3vi4wV56DNPRuqQCbk8knqXvqBKZSk6iJC8CS9YNoQkyUSLtkwz9kSUCH0e27ZNIGM-lyBnJEiILYcqLzyT94Kvwk0jSeQI3va7P-jp-cvCjn4B5uXT1UygukoWoAEFw1dF9EzGNcD3aNLREq8njCeUWsiJhnkH173mq_728hlLfdwfB4NF7PocDqXcVZqUXUESBxSXa6YxfKQV_A3kNmV4
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Apatent&rft.title=Protective+dismantling+construction+method+for+basement+pile+foundation+adjacent+to+existing+subway+line&rft.inventor=LIU+ZIYANG&rft.inventor=WANG+JIE&rft.inventor=DU+YAO&rft.inventor=JIN+PING&rft.inventor=WANG+SHENGTAO&rft.inventor=ZHAO+GAOFENG&rft.inventor=DENG+NENGWEI&rft.inventor=ZHAO+RAN&rft.inventor=CHEN+TAO&rft.inventor=LI+RAN&rft.inventor=WANG+YANG&rft.inventor=WU+JIALIN&rft.inventor=DU+HONGBO&rft.inventor=FANG+ZHIHAI&rft.inventor=DENG+XIFEI&rft.inventor=ZHANG+GUANGHUI&rft.date=2022-08-30&rft.externalDBID=A&rft.externalDocID=CN114961336A