Up-down separate excavation type construction method for underground channel transversely penetrating through lower part of upper building pile foundation
The invention discloses an up-down separate excavation type construction method for an underground channel transversely penetrating through the lower part of an upper building pile foundation. The up-down separate excavation type construction method comprises the steps that a working well is built;...
Saved in:
Main Authors | , , , , , , , , |
---|---|
Format | Patent |
Language | Chinese English |
Published |
28.12.2021
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | The invention discloses an up-down separate excavation type construction method for an underground channel transversely penetrating through the lower part of an upper building pile foundation. The up-down separate excavation type construction method comprises the steps that a working well is built; the whole section is dug to the position with the distance D away from a first row of pile foundations of an upper building to form a first-section blank channel, and a first-section blank channel part channel protection wall frame is poured in the first-section blank channel; on the premise that a soil body on the lower part of the first row of pile foundations is reserved, excavation continues to be carried out to the position with the distance D from a second row of pile foundations of the upper building, so that a second-section blank channel and the upper half part of the first row of pile foundation blank channel are formed; and the upper half part of a pouring pile foundation underpinning structure and a sec |
---|---|
Bibliography: | Application Number: CN202110809090 |