Construction method of vertical shaft starting device for top-down pipe-jacking construction in shield tunnel
The invention discloses a construction method of a vertical shaft starting device for top-down pipe-jacking construction in a shield tunnel. According to the method, a pipe jacking machine and a matched trolley are transported to a vertical shaft construction position, an initial position is adjuste...
Saved in:
Main Authors | , , , , , , , , |
---|---|
Format | Patent |
Language | Chinese English |
Published |
15.01.2021
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | The invention discloses a construction method of a vertical shaft starting device for top-down pipe-jacking construction in a shield tunnel. According to the method, a pipe jacking machine and a matched trolley are transported to a vertical shaft construction position, an initial position is adjusted, a pipe piece supporting system is adjusted to a working position, a tunnel guide rail at the bottom of equipment is dismounted, a recyclable pipe jacking main machine is made to descend to the contact position capable of directly cutting a composite pipe piece through a crane, a starting steel sleeve is welded, the space between shield tail brushes is filled with grease, and a pipe jacking piece is hoisted to the construction position every time the pipe jacking machine tunnels to a certain position. By means of a matched trolley system and a crane pipe jacking supporting and jacking system, equipment can be integrally conveyed into a main tunnel or conveyed from the main tunnel, mountingand dismounting are conv |
---|---|
Bibliography: | Application Number: CN202011461219 |