Method for constructing tunnel by utilizing shield empty-pushing crossing mine method

The invention discloses a method for constructing a tunnel by utilizing a shield empty-pushing crossing mine method. Gravels are paved in advance on an empty-pushing section, thereby being short in construction period; the gravels are stacked and filled in front of a cutter, a counter force is provi...

Full description

Saved in:
Bibliographic Details
Main Authors DUAN SHAOHE, CHEN QIANG, LUO SHIBAO, QING SANHUI, WANG JIAXIANG, HE QIHAI
Format Patent
LanguageChinese
English
Published 25.04.2012
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:The invention discloses a method for constructing a tunnel by utilizing a shield empty-pushing crossing mine method. Gravels are paved in advance on an empty-pushing section, thereby being short in construction period; the gravels are stacked and filled in front of a cutter, a counter force is provided when the shield is in a tunneling process, and duct pieces are not fixed by structural steel; most clearances between the duct pieces and rock are filled with the gravels, thereby reducing work load and promoting tunneling efficiency; enough counter force is supplied by a jack for splicing the duct pieces, a water-stopping bar is excellently pasted and a waterproof effect is excellent; the duct pieces can be filled and compacted in time, the duct pieces after being spliced cannot float upward, and damaged and over-loaded staggered slabs do not exist; the grout amount on the back of the duct pieces is reduced and the construction cost is saved; and the tunneling efficiency is greatly promoted, the production val
Bibliography:Application Number: CN20111451093