Effect of soil set-up on the capacity of jacked concretepipe piles in mixed soils

The increase in capacity of displacement piles with time after installation is typically known as soil/pile set-up. A full-scale field test is carried out to observe the set-up effect for open-ended concrete pipe piles jacked into mixed soils. Both the total capacity and the average unit shaft resis...

Full description

Saved in:
Bibliographic Details
Published in浙江大学学报:A卷英文版 Vol. 12; no. 8; pp. 637 - 644
Main Author Jun-wei LIU Zhong-miao ZHANG Feng YU Cun-gang LIN
Format Journal Article
LanguageEnglish
Published 2011
Online AccessGet full text

Cover

Loading…
More Information
Summary:The increase in capacity of displacement piles with time after installation is typically known as soil/pile set-up. A full-scale field test is carried out to observe the set-up effect for open-ended concrete pipe piles jacked into mixed soils. Both the total capacity and the average unit shaft resistance increase approximately linearly with logarithmic time. The average increase rate for unit shaft resistance is 44% per log cycle, while the average increase for total capacity is approximately 21%. A review on case histories for long-term set-up indicates an average set-up rate of approximately 40%. Based on this, the mechanism of pile set-up is discussed in detail and a three-phase model is suggested.
Bibliography:The increase in capacity of displacement piles with time after installation is typically known as soil/pile set-up. A full-scale field test is carried out to observe the set-up effect for open-ended concrete pipe piles jacked into mixed soils. Both the total capacity and the average unit shaft resistance increase approximately linearly with logarithmic time. The average increase rate for unit shaft resistance is 44% per log cycle, while the average increase for total capacity is approximately 21%. A review on case histories for long-term set-up indicates an average set-up rate of approximately 40%. Based on this, the mechanism of pile set-up is discussed in detail and a three-phase model is suggested.
Concrete pipe pile, Jack piling, Set-up, Pile capacity
33-1236/O4
Jun-wei LIU, Zhong-miao ZHAN, Feng YU, Cun-gang LIN ( MOE Key Laboratory of Soft Soil and Geoenvironmental Engineering, Institute of Geoteehnical Engineering, Zhejiang University, Hangzhou 310058, China)
ISSN:1673-565X