ASPECTS REGARDING THE EFFICIENCY ACHIEVEDBY REPLACING THE AUXILIARY GENERATOR WITH ELECTRICAL TRANSFORMER OF 20 / 0.6 KV AT THE SYNCHRONOUS GENERATORS OF 330 MW

In this paper is being analyzed the possibly of replacing the auxiliary generator of a synchronous generator of 330 MW with an electrical transformer with transforming report of 20 / 0.6 kVconnected to the generator stator winding terminals. In this paper is presented how to replace the auxiliary ge...

Full description

Saved in:
Bibliographic Details
Published inInternational Multidisciplinary Scientific GeoConference : SGEM Vol. 2; pp. 79 - 84
Main Authors Popescu, Cristinel, Racoceanu, Cristinel
Format Conference Proceeding
LanguageEnglish
Published Sofia Surveying Geology & Mining Ecology Management (SGEM) 01.01.2016
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:In this paper is being analyzed the possibly of replacing the auxiliary generator of a synchronous generator of 330 MW with an electrical transformer with transforming report of 20 / 0.6 kVconnected to the generator stator winding terminals. In this paper is presented how to replace the auxiliary generator related to a synchronous generator of 330 MW and the efficiency broughtto the monitoring, adjustmentand control system of the excitation of a synchronous generator of 330 MW.
ISSN:1314-2704