Analysis of relay protection action of grounding fault of no-load charging of a 330 kV transformer
In view of problem that a 330 kV start-up standby transformer took place relay protection action in no-load charging, the paper indicated that the action was caused by grounding fault of A-phase current transformer through analyzing charging current waveform recorded by electric quantity analyzer, a...
Saved in:
Published in | Gong kuang zi dong hua = Industry and mine automation Vol. 39; no. 5; pp. 63 - 66 |
---|---|
Main Authors | , , , |
Format | Journal Article |
Language | Chinese |
Published |
Editorial Department of Industry and Mine Automation
01.05.2013
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | In view of problem that a 330 kV start-up standby transformer took place relay protection action in no-load charging, the paper indicated that the action was caused by grounding fault of A-phase current transformer through analyzing charging current waveform recorded by electric quantity analyzer, and gave several suggestions to improve safety and reliability of charging test of large-scale transformer: strengthen insulation inspection for current and voltage transformers of high-voltage side of transformer; properly increase sensitivity of main and backup protection to prevent relay protection action by inrush current; it should record for three-phase current and voltage of high-voltage side of transformer in charging process. |
---|---|
ISSN: | 1671-251X |
DOI: | 10.7526/j.issn.1671-251X.2013.05.018 |