Deformation characteristics and safety assessment of a high-speed railway induced by undercutting metro tunnel excavation

Stratum deformation (settlement) is a challenging issue in tunnel engineering, especially when construction of metro tunnels has to undercut high-speed railway. For this purpose, we used the FLAC3D software to analyze the stratum settlement characteristics of high-speed railway at different crossing...

Full description

Saved in:
Bibliographic Details
Published inJournal of Rock Mechanics and Geotechnical Engineering Vol. 11; no. 1; pp. 88 - 98
Main Authors Qian, Wangping, Qi, Taiyue, Zhao, Yunjian, Le, Yizhou, Yi, Haiyang
Format Journal Article
LanguageEnglish
Published Elsevier B.V 01.02.2019
School of Civil Engineering, Southwest Jiaotong University, Chengdu, 610031, China%China Railway Design Corporation, Tianjin, 300142, China%China Changjiang Construction Investment Corp. Ltd., Chengdu, 610000, China%North China Institute of Science and Technology, Langfang, 065201, China
Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University, Chengdu, 610031, China
Elsevier
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:Stratum deformation (settlement) is a challenging issue in tunnel engineering, especially when construction of metro tunnels has to undercut high-speed railway. For this purpose, we used the FLAC3D software to analyze the stratum settlement characteristics of high-speed railway at different crossing angles intersected by metro tunnel, in terms of ground settlement trough, stratum slip line and irregularity of ballastless tracks. According to the evolution of the stratum settlement at different angle regions, an optimized angle is proposed for the actual project design. In order to reduce the influence of stratum settlement on the safety of high-speed railway, an approach of safety assessment is proposed for the shield engineering undercutting high-speed railway, as per Chinese specifications using numerical results and on-site conditions. A case study is conducted for the shield tunnel section crossing the Wuhan – Guangzhou High-speed Railway between the Guangzhou North Railway Station and the Huacheng Road Station, which represents the first metro tunnel project passing below a high-speed railway in China. A series of measures is taken to ensure the safe excavation of the shield tunnel and the operation of the high-speed railway. The results can provide a technical support for performing a safety evaluation between high-speed railways and metro tunnels.
ISSN:1674-7755
DOI:10.1016/j.jrmge.2018.04.014