A project for verification of HTS power cable system by KEPCO (Korea Electric Power Corporation) was started in 2002. The HTS power cable system of 100 m, 22.9 kV, 1.25 kA has been installed and tested at the KEPCO's Gochang power testing center in Korea since 2006. A liquid nitrogen decompress...

Full description

Saved in:
Bibliographic Details
Published inIEEE transactions on applied superconductivity Vol. 19; no. 3; pp. 1782 - 1784
Main Authors Yang, Hyung Suk, Kim, Dong Lak, Sohn, Song Ho, Lim, Ji Hyun, Choi, Ha Ok, Choi, Yeon Suk, Lee, Byoung Seob, Jung, Won Moog, Ryoo, Hee Suk, Hwang, Si Dole
Format Journal Article Conference Proceeding
LanguageEnglish
Published New York, NY IEEE 01.06.2009
Institute of Electrical and Electronics Engineers
The Institute of Electrical and Electronics Engineers, Inc. (IEEE)
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:A project for verification of HTS power cable system by KEPCO (Korea Electric Power Corporation) was started in 2002. The HTS power cable system of 100 m, 22.9 kV, 1.25 kA has been installed and tested at the KEPCO's Gochang power testing center in Korea since 2006. A liquid nitrogen decompression cooling system with a cooling capacity of 3 kW at 66 K and a closed-circulation system of subcooled liquid nitrogen were employed for this purpose. Several performance tests for the HTS power cable system, such as cooling capacity, electrical loading, heat load, AC loss and temperature stability, were performed at operating temperature of 66.4 K. Thermal cycle test including cool-down to liquid nitrogen temperature and warming up to room temperature, was also performed to investigate thermal cycle influences for 8 times. The reliability through the several demonstration tests over than 8,000 hours was proved.
Bibliography:ObjectType-Article-2
SourceType-Scholarly Journals-1
ObjectType-Feature-1
content type line 23
ISSN:1051-8223
1558-2515