The impact of flexibility on engineer-to-order production planning

This paper addresses the tactical production planning problem of engineer-to-order companies. For this, we extend the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP) to the multi-project case as well as flexible resource availability. We model the problem as...

Full description

Saved in:
Bibliographic Details
Published inInternational journal of production economics Vol. 239; p. 108183
Main Authors Brachmann, Robert, Kolisch, Rainer
Format Journal Article
LanguageEnglish
Published Elsevier B.V 01.09.2021
Elsevier Science Publishers
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:This paper addresses the tactical production planning problem of engineer-to-order companies. For this, we extend the resource-constrained project scheduling problem with flexible resource profiles (FRCPSP) to the multi-project case as well as flexible resource availability. We model the problem as a deterministic discrete-time mixed-integer program using step-variables. For each activity the start time, the duration, and the allocation of a given resource requirement over time has to be determined, taking into account precedence constraints between activities and availability of resources. The capacity of resources is not fixed but can vary subject to working time accounts. Using a lexicographic ordering approach, the primary objective is to minimize the total weighted lateness of projects, while the secondary objective is to balance working time accounts. In our computational study, we solve real-world instances from a mid-size company with up to 100 projects and 1725 activities. We show that optimal solutions can be derived in reasonable computation time with off-the-shelf commercial solvers. From a managerial point of view, our results demonstrate the value of flexibility.
ISSN:0925-5273
1873-7579
DOI:10.1016/j.ijpe.2021.108183