Activity measurements and calculations for gamma-emitting radionuclides in concrete drill cores of unit 2 of the Greifswald NPP
Due to Germany’s nuclear phase-out, decommissioning and final disposal of construction materials of Nuclear Power Plants (NPP) become increasingly important. The reliable determination of radionuclides produced by neutron activation, the activity as a function of time since shutdown and investigatio...
Saved in:
Published in | EPJ Web of conferences Vol. 308; p. 3005 |
---|---|
Main Authors | , , , |
Format | Journal Article Conference Proceeding |
Language | English |
Published |
Les Ulis
EDP Sciences
01.01.2024
|
Subjects | |
Online Access | Get full text |
ISSN | 2100-014X 2101-6275 2100-014X |
DOI | 10.1051/epjconf/202430803005 |
Cover
Loading…
Summary: | Due to Germany’s nuclear phase-out, decommissioning and final disposal of construction materials of Nuclear Power Plants (NPP) become increasingly important. The reliable determination of radionuclides produced by neutron activation, the activity as a function of time since shutdown and investigation of subsequent radionuclide mobility are subject of a research project. Drill cores of the concrete shielding of unit 2 of the Greifswald NPP were retrieved. Specific activities of gamma emitters and the elemental composition were measured. The radiation transport code MCNP 6 was used for the calculation of spectral neutron fluences. A neutron radiation field calculation reveals that the maximum neutron fluence at the concrete component is located in the floor just below the RPV. The concrete structures closest to the reactor core are shielded efficiently against neutron radiation by the annular water tank. Measured and calculated specific activities of
152
Eu,
154
Eu and
60
Co for the cement screed at the position of the maximum neutron fluence are surprisingly low. A specific exemption (i.e. release from radiation protection surveillance but mandatory for final disposal) of the screed sample according to Germany’s Radiation Protection Ordnance is expected to be possible approximately 4 decades after the shutdown of the NPP. |
---|---|
Bibliography: | ObjectType-Conference Proceeding-1 SourceType-Conference Papers & Proceedings-1 content type line 21 |
ISSN: | 2100-014X 2101-6275 2100-014X |
DOI: | 10.1051/epjconf/202430803005 |