Floor defects in quarters over railway tunnel caused by design and construction errors
The main subject of this paper is a floor in the quarters located above the railway tunnel in the large-area Shopping Center. The considered floor did not meet the satisfactory safety conditions, as a result of design and construction errors, which were a direct cause of the failure. In the long ter...
Saved in:
Published in | MATEC Web of Conferences Vol. 284; p. 4005 |
---|---|
Main Authors | , , |
Format | Journal Article Conference Proceeding |
Language | English |
Published |
Les Ulis
EDP Sciences
2019
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | The main subject of this paper is a floor in the quarters located above the railway tunnel in the large-area Shopping Center. The considered floor did not meet the satisfactory safety conditions, as a result of design and construction errors, which were a direct cause of the failure. In the long term, failure could lead to a construction disaster. |
---|---|
ISSN: | 2261-236X 2274-7214 2261-236X |
DOI: | 10.1051/matecconf/201928404005 |