Reliability Allocation of Large Mining Excavator Electrical System Based on the Entropy Method with Failure and Maintenance Data

In the design of large mining excavator electrical system,a practical reliability allocation method was introduced to allocate system level reliability requirements into subsystem and component levels. During the reliability allocation process,factors from the fault and maintenance data were only co...

Full description

Saved in:
Bibliographic Details
Published in东华大学学报(英文版) Vol. 31; no. 6; pp. 779 - 781
Main Author 胡天松 黄洪钟 王晓明 李光 高素荷
Format Journal Article
LanguageEnglish
Published School of Mechanical Electronic and Industrial Engineering, University of Electronic Science and Technology of China, Chengdu 611731, China%Taiyuan Heavy Industry Co., Ltd., Taiyuan 030024, China 31.12.2014
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:In the design of large mining excavator electrical system,a practical reliability allocation method was introduced to allocate system level reliability requirements into subsystem and component levels. During the reliability allocation process,factors from the fault and maintenance data were only considered in reliability allocation scheme. It could avoid the disturbance from expert experiences. The entropy method was also used to obtain weights of reliability allocation indexes of large mining excavators considering different factors. Then the failure rate allocation of subsystems and components could be completed.
Bibliography:reliability allocation large mining excavators the entropy method
31-1920/N
HU Tian-song, HUANG Hong-zhong, WANG Xiao-ming, LI Guang, GAO Su-he 1 School of Mechanical Electronic and Industrial Engineering, University of Electronic Science and Technology of China, Chengdu 611731, China 2 Taiyuan Heavy Industry Co. , Ltd. , Taiyuan 030024, China
In the design of large mining excavator electrical system,a practical reliability allocation method was introduced to allocate system level reliability requirements into subsystem and component levels. During the reliability allocation process,factors from the fault and maintenance data were only considered in reliability allocation scheme. It could avoid the disturbance from expert experiences. The entropy method was also used to obtain weights of reliability allocation indexes of large mining excavators considering different factors. Then the failure rate allocation of subsystems and components could be completed.
ISSN:1672-5220