TUNNEL LINING CONSTRUCTION METHOD
PROBLEM TO BE SOLVED: To provide a construction method for filling a form for tunnel lining with concrete at a high density to form a tunnel lining having excellent durability. SOLUTION: In a process for placing concrete for the lining by installing the form in a tunnel, the pressure of concrete fil...
Saved in:
Main Authors | , , |
---|---|
Format | Patent |
Language | English |
Published |
17.04.2008
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Summary: | PROBLEM TO BE SOLVED: To provide a construction method for filling a form for tunnel lining with concrete at a high density to form a tunnel lining having excellent durability. SOLUTION: In a process for placing concrete for the lining by installing the form in a tunnel, the pressure of concrete filled into the form 1 is measured by pressure measuring means 15, 16 to adjust the pressure of the concrete 9 filled into the form 1 to such a range that prevents the deformation or breakage of the form 1. Concrete is pressed in through a first blow-up port 11 in a crest formed at the lap side 24 of a space partitioned by the form 1, and the concrete 9 is compacted by a vibrator 8 after filling the form 1 with the concrete. Then, the concrete is further pressed in through a second blow-up port 11c in a crest formed at the end side 25 of the form. COPYRIGHT: (C)2008,JPO&INPIT |
---|---|
Bibliography: | Application Number: JP20060270631 |