Construction method for civil air defense construction engineering in reverse construction method in case of thick water-containing sand layer

The invention relates to a construction method of a civil air defense building engineering reverse construction method meeting a thick water-containing sand layer, which comprises the following steps: firstly, paying off and positioning, then constructing a support pile, pouring an underground diaph...

Full description

Saved in:
Bibliographic Details
Main Authors GUO HONGCHENG, ZHOU CHENGCAI, WANG JINXING, CHEN QIANG, TENG ZHONGJIE, ZHANG RONGHUI, GAO SHUNLAI
Format Patent
LanguageChinese
English
Published 19.04.2024
Subjects
Online AccessGet full text

Cover

Loading…
Abstract The invention relates to a construction method of a civil air defense building engineering reverse construction method meeting a thick water-containing sand layer, which comprises the following steps: firstly, paying off and positioning, then constructing a support pile, pouring an underground diaphragm wall around a building as an enclosure wall of a foundation pit support structure, drilling according to a pile position, and then lowering a first reinforcement cage; and in the process of lowering the first reinforcement cage, a prefabricated connecting piece is installed on the first reinforcement cage, then concrete is poured to form a supporting pile, and ring beam construction and floor slab construction are conducted in sequence. The connecting structure has the effect of improving the connecting strength of the structural beam and the supporting piles. 本申请涉及一种人防建筑工程逆作法遇厚层含水沙层施工方法,首先进行放线定位,接着进行支撑桩施工,沿建筑物周围浇注地下连续墙,作为基坑支护结构的围护墙,并根据桩位进行钻孔,然后下放第一钢筋笼,下放第一钢筋笼的过程中在第一钢筋笼上安装预制连接件,之后浇筑混凝土以形成支撑桩,依次进行环梁施工和楼板施工。本申请具
AbstractList The invention relates to a construction method of a civil air defense building engineering reverse construction method meeting a thick water-containing sand layer, which comprises the following steps: firstly, paying off and positioning, then constructing a support pile, pouring an underground diaphragm wall around a building as an enclosure wall of a foundation pit support structure, drilling according to a pile position, and then lowering a first reinforcement cage; and in the process of lowering the first reinforcement cage, a prefabricated connecting piece is installed on the first reinforcement cage, then concrete is poured to form a supporting pile, and ring beam construction and floor slab construction are conducted in sequence. The connecting structure has the effect of improving the connecting strength of the structural beam and the supporting piles. 本申请涉及一种人防建筑工程逆作法遇厚层含水沙层施工方法,首先进行放线定位,接着进行支撑桩施工,沿建筑物周围浇注地下连续墙,作为基坑支护结构的围护墙,并根据桩位进行钻孔,然后下放第一钢筋笼,下放第一钢筋笼的过程中在第一钢筋笼上安装预制连接件,之后浇筑混凝土以形成支撑桩,依次进行环梁施工和楼板施工。本申请具
Author GAO SHUNLAI
CHEN QIANG
ZHANG RONGHUI
TENG ZHONGJIE
WANG JINXING
ZHOU CHENGCAI
GUO HONGCHENG
Author_xml – fullname: GUO HONGCHENG
– fullname: ZHOU CHENGCAI
– fullname: WANG JINXING
– fullname: CHEN QIANG
– fullname: TENG ZHONGJIE
– fullname: ZHANG RONGHUI
– fullname: GAO SHUNLAI
BookMark eNqNzL0KwjAUxfEMOvj1DtcHKLSIqKMUxcnJvYT0pL1Yb0oSK76Ez2yFDuLkdIb_jzNVI3GCiXrlTkL0dxPZCd0Qa1eSdZ4Md9yQZk8lLCSAzLeEVCyAZ6mIhTw6-F8zvPXZ6L45S7Fmc6WHjvBJT6Nm-RwELSU1-gk_V2Orm4DFsDO1PB4u-SlB6wqEVhsIYpGfs2yzS9dZut2v_jFvLNhRQA
ContentType Patent
DBID EVB
DatabaseName esp@cenet
DatabaseTitleList
Database_xml – sequence: 1
  dbid: EVB
  name: esp@cenet
  url: http://worldwide.espacenet.com/singleLineSearch?locale=en_EP
  sourceTypes: Open Access Repository
DeliveryMethod fulltext_linktorsrc
Discipline Medicine
Chemistry
Sciences
DocumentTitleAlternate 一种人防建筑工程逆作法遇厚层含水沙层施工方法
ExternalDocumentID CN117905108A
GroupedDBID EVB
ID FETCH-epo_espacenet_CN117905108A3
IEDL.DBID EVB
IngestDate Fri Aug 02 08:56:46 EDT 2024
IsOpenAccess true
IsPeerReviewed false
IsScholarly false
Language Chinese
English
LinkModel DirectLink
MergedId FETCHMERGED-epo_espacenet_CN117905108A3
Notes Application Number: CN202410315046
OpenAccessLink https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20240419&DB=EPODOC&CC=CN&NR=117905108A
ParticipantIDs epo_espacenet_CN117905108A
PublicationCentury 2000
PublicationDate 20240419
PublicationDateYYYYMMDD 2024-04-19
PublicationDate_xml – month: 04
  year: 2024
  text: 20240419
  day: 19
PublicationDecade 2020
PublicationYear 2024
RelatedCompanies FUJIAN YIJIAN GROUP CO., LTD
RelatedCompanies_xml – name: FUJIAN YIJIAN GROUP CO., LTD
Score 3.6487818
Snippet The invention relates to a construction method of a civil air defense building engineering reverse construction method meeting a thick water-containing sand...
SourceID epo
SourceType Open Access Repository
SubjectTerms BUILDING
BUILDING MATERIALS
EMBANKMENTS
EXCAVATIONS
FIXED CONSTRUCTIONS
FOUNDATIONS
HYDRAULIC ENGINEERING
SOIL SHIFTING
STRUCTURAL ELEMENTS
UNDERGROUND OR UNDERWATER STRUCTURES
Title Construction method for civil air defense construction engineering in reverse construction method in case of thick water-containing sand layer
URI https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20240419&DB=EPODOC&locale=&CC=CN&NR=117905108A
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV1LS8NAEB5qFfWmVdH6YATpLdg0jzaHIHbTUISmRar0VpLNLo2WtLTFgj_C3-xsmtoi6C3sLsPuhC8zk535BuCOYmRDOpal1WJeowCFS4KUaWh2GAoyCXpdZoXCncBuv5hPA2tQgLd1LUzGE7rMyBEJUZzwvsi-19PNTywvy62c30cJDU0e_L7rVfLomMyTSQj0mm6r1_W6rMKYy4JK8OzqKyaqauNxB3aVG6149luvTVWVMt02Kf4R7PVIWro4hsLnqAQHbN15rQT7nfzCmx5z7M1P4Ev11lyzveKq8zOSy4k8-UjGGCYzjIWkqFQg314pNoyDmKSoKJtmv9fk0miak1XDiUSVBv-OS9riTFPp7KtGEjgP0xjHIfnpp3Drt_qsrdHBhj9aHLJgowPjDIrpJBXngMLkVTMir0QSMkWj5ghHyMi0LSeO65GuX0D5bznl_yYv4VC9EXX1ojtXUKQziWuy4IvoJlP9NyKGpAw
link.rule.ids 230,309,786,891,25594,76906
linkProvider European Patent Office
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV1LT8JAEJ4gGvGmqEF8jYnh1kihBXpojGwhqFCIQcONtNvdWCWFAJHEH-FvdrYUISZ6a3Y3k33k25npznwDcE0-cllapqmVAl4iB4VLgpRR1iqeJ0gl6FUZJwp33Err2XgYmIMUvK1yYWKe0EVMjkiI4oT3eXxfT9Y_sZw4tnJ244fUNL5t9m2nkHjHpJ4MQqBTtxu9rtNlBcZs5hbcJ1tfMlEVa3dbsF1V7LzKdHqpq6yUyaZKae7DTo-kRfMDSH2-ZiHDVpXXsrDbSR686TPB3uwQvlRtzRXbKy4rPyOZnMjDj3CEXjjFQEjySgXyzZFizTiIYYSKsmn6e0wijbo5aTUcS1Rh8O-4oClONRXOviwkgTMvCnDkkZ1-BFfNRp-1NFrY8GcXh8xd70H5GNLROBI5QGHwouGTVSIJmaJWsoQlpG9UTCsIqr6un0D-bzn5_zovIdPqd9rD9r37eAp76nTUM4xunUGa1ifOSZvP_Yv4GL4B-L2m-Q
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Apatent&rft.title=Construction+method+for+civil+air+defense+construction+engineering+in+reverse+construction+method+in+case+of+thick+water-containing+sand+layer&rft.inventor=GUO+HONGCHENG&rft.inventor=ZHOU+CHENGCAI&rft.inventor=WANG+JINXING&rft.inventor=CHEN+QIANG&rft.inventor=TENG+ZHONGJIE&rft.inventor=ZHANG+RONGHUI&rft.inventor=GAO+SHUNLAI&rft.date=2024-04-19&rft.externalDBID=A&rft.externalDocID=CN117905108A