Super-long basement seamless structure construction method
The invention relates to a construction method for a seamless structure of a super-long basement, and relates to the technical field of basement construction. The method comprises the following steps that S1, a foundation pit of a first area is dug, and the foundation pit of the first area is suppor...
Saved in:
Main Authors | , , , , , |
---|---|
Format | Patent |
Language | Chinese English |
Published |
06.12.2022
|
Subjects | |
Online Access | Get full text |
Cover
Loading…
Abstract | The invention relates to a construction method for a seamless structure of a super-long basement, and relates to the technical field of basement construction. The method comprises the following steps that S1, a foundation pit of a first area is dug, and the foundation pit of the first area is supported through supporting piles; s2, reinforcing meshes are bound on the inner bottom wall and the inner side wall of the foundation pit in the first area; s3, reinforcing steel bars are arranged on the inner bottom wall of the foundation pit in the first area, and then concrete mortar is poured on the inner bottom wall and the inner side wall of the foundation pit in the first area and leveled to form a bottom layer and a side layer; and S4, after the bottom layer and the side layer are stable, repeating the operation steps of S1 to S3 to form the bottom layer and the side layer of the second area. The effect of improving the overall strength of the whole basement is achieved.
本申请涉及一种超长地下室无缝结构施工方法,涉及地下室施工技术领域。其包括以下步骤 |
---|---|
AbstractList | The invention relates to a construction method for a seamless structure of a super-long basement, and relates to the technical field of basement construction. The method comprises the following steps that S1, a foundation pit of a first area is dug, and the foundation pit of the first area is supported through supporting piles; s2, reinforcing meshes are bound on the inner bottom wall and the inner side wall of the foundation pit in the first area; s3, reinforcing steel bars are arranged on the inner bottom wall of the foundation pit in the first area, and then concrete mortar is poured on the inner bottom wall and the inner side wall of the foundation pit in the first area and leveled to form a bottom layer and a side layer; and S4, after the bottom layer and the side layer are stable, repeating the operation steps of S1 to S3 to form the bottom layer and the side layer of the second area. The effect of improving the overall strength of the whole basement is achieved.
本申请涉及一种超长地下室无缝结构施工方法,涉及地下室施工技术领域。其包括以下步骤 |
Author | GONG DEJIN XIONG ZHIBING CHEN WENXIANG FENG BO ZHOU YAN GUO BINGLIN |
Author_xml | – fullname: CHEN WENXIANG – fullname: GONG DEJIN – fullname: FENG BO – fullname: GUO BINGLIN – fullname: XIONG ZHIBING – fullname: ZHOU YAN |
BookMark | eNrjYmDJy89L5WSwCi4tSC3SzcnPS1dISixOzU3NK1EoTk3MzUktLlYoLikqTS4pLUpVSM7Pg3Ay8_MUclNLMvJTeBhY0xJzilN5oTQ3g6Kba4izh25qQX58anFBYnJqXmpJvLOfoaGpibGJsZmpozExagDkoTG0 |
ContentType | Patent |
DBID | EVB |
DatabaseName | esp@cenet |
DatabaseTitleList | |
Database_xml | – sequence: 1 dbid: EVB name: esp@cenet url: http://worldwide.espacenet.com/singleLineSearch?locale=en_EP sourceTypes: Open Access Repository |
DeliveryMethod | fulltext_linktorsrc |
Discipline | Medicine Chemistry Sciences |
DocumentTitleAlternate | 一种超长地下室无缝结构施工方法 |
ExternalDocumentID | CN115434365A |
GroupedDBID | EVB |
ID | FETCH-epo_espacenet_CN115434365A3 |
IEDL.DBID | EVB |
IngestDate | Fri Jul 19 13:01:11 EDT 2024 |
IsOpenAccess | true |
IsPeerReviewed | false |
IsScholarly | false |
Language | Chinese English |
LinkModel | DirectLink |
MergedId | FETCHMERGED-epo_espacenet_CN115434365A3 |
Notes | Application Number: CN202211158839 |
OpenAccessLink | https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20221206&DB=EPODOC&CC=CN&NR=115434365A |
ParticipantIDs | epo_espacenet_CN115434365A |
PublicationCentury | 2000 |
PublicationDate | 20221206 |
PublicationDateYYYYMMDD | 2022-12-06 |
PublicationDate_xml | – month: 12 year: 2022 text: 20221206 day: 06 |
PublicationDecade | 2020 |
PublicationYear | 2022 |
RelatedCompanies | CHINA ANNENG GROUP SECOND ENGINEERING BUREAU CO., LTD |
RelatedCompanies_xml | – name: CHINA ANNENG GROUP SECOND ENGINEERING BUREAU CO., LTD |
Score | 3.5702608 |
Snippet | The invention relates to a construction method for a seamless structure of a super-long basement, and relates to the technical field of basement construction.... |
SourceID | epo |
SourceType | Open Access Repository |
SubjectTerms | EMBANKMENTS EXCAVATIONS FIXED CONSTRUCTIONS FOUNDATIONS HYDRAULIC ENGINEERING SOIL SHIFTING UNDERGROUND OR UNDERWATER STRUCTURES |
Title | Super-long basement seamless structure construction method |
URI | https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20221206&DB=EPODOC&locale=&CC=CN&NR=115434365A |
hasFullText | 1 |
inHoldings | 1 |
isFullTextHit | |
isPrint | |
link | http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwY2BQMU2yTElMTErVNUsyNdc1STM2B2YpSwvdNNNEA8sUA-NUM_Cud18_M49QE68I0wgmhizYXhjwOaHl4MMRgTkqGZjfS8DldQFiEMsFvLayWD8pEyiUb-8WYuuiBu0dGwELYgMzNRcnW9cAfxd_ZzVnZ1tnPzW_IFvQqTPGJsZmpo7MDKygZjTonH3XMCfQrpQC5CrFTZCBLQBoWl6JEANTVYYwA6cz7OY1YQYOX-iEN5AJzXvFIgxWwaUFqUW6Ofl56Qqgugc0rKcATKi5OcDCSgFyDmxpUapCcj7iUFgFyAXRogyKbq4hzh66QEfEw30c7-yHcK-xGANLXn5eqgSDgmliWlqahaFJalpKikliIrA3YmyWBNrLbmCQmAos2iQZpHCbI4VPUpqBCxR64HUaZjIMLEBnpsoCa9uSJDlwMAEANSeE6Q |
link.rule.ids | 230,309,786,891,25594,76903 |
linkProvider | European Patent Office |
linkToHtml | http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV3dS8MwED_mFOebTkXnVwXpW7GaNt2EIi7dmLp2Q6fsbSRr4gezHftA8K_3mm3OF30LCRyXI3fHXe5-B3DmikrMuZAWFa5nOYp4qFKVsqVcbldim0iqu97DiDaenLuu283B-6IXRuOEfmpwRNSoPur7RNvr4TKJFejayvG5eMOt9Lre8QNzHh1foiG2qRlU_Vq7FbSYyZjPIjN68DPUGeIQ6t6swKqHIaEOlZ6rWVfK8LdLqW_CWhupJZMtyH29FqHAFpPXirAezj-8cTnXvfE2XD1Oh3JkDdLkxch8T5bWM_ChfgzQWBkzHNjpSBr9dAkKa8wGRO_Aab3WYQ0Lmej93LjHoiW_ZBfySZrIPTBcrpQqXzhSxbHDOUYjhIqsl922uUTTtg-lv-mU_js8gUKjEzZ7zdvo_gA2Mknqmg16CHlkWR6h552IYy2yb5FVh9M |
openUrl | ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Apatent&rft.title=Super-long+basement+seamless+structure+construction+method&rft.inventor=CHEN+WENXIANG&rft.inventor=GONG+DEJIN&rft.inventor=FENG+BO&rft.inventor=GUO+BINGLIN&rft.inventor=XIONG+ZHIBING&rft.inventor=ZHOU+YAN&rft.date=2022-12-06&rft.externalDBID=A&rft.externalDocID=CN115434365A |