Method for building a bridge and bridge-building apparatus

A method for building a bridge, said bridge (4) comprising piers (6) and at least one deck (8), the method comprising: - a cantilever step, wherein a girder (16) is set in a cantilevered position relative to a bank or to a constructed zone (12) of the bridge so that the girder comprises a first end...

Full description

Saved in:
Bibliographic Details
Main Authors GABALDO STEFANO L, BERMINGHAM PATRICK D, LE TREUT BRICE, MELLIER ERIK
Format Patent
LanguageChinese
English
Published 19.04.2017
Subjects
Online AccessGet full text

Cover

Loading…
Abstract A method for building a bridge, said bridge (4) comprising piers (6) and at least one deck (8), the method comprising: - a cantilever step, wherein a girder (16) is set in a cantilevered position relative to a bank or to a constructed zone (12) of the bridge so that the girder comprises a first end (24) overhanging the bank or the constructed zone, and a second end (26) overhanging a construction zone (14) of the bridge, - a construction step, wherein pier elements and deck elements (10) are installed in said construction zone (14) via a first and a second lifting devices (18, 20) mounted movable on the girder (16) between the first and second ends (24, 26). The first and second lifting devices (18, 20) cross one another along the girder during the cantilever step and/or during the construction step. Associated bridge-building apparatus. 种建造桥梁的方法,所述桥梁(4)包括桥墩(6)以及至少个桥面(8),该方法包括:-悬臂步骤,其中,把主梁(16)设置在与河岸或桥梁建成区(12)相对的悬臂位置,所以主梁包括悬于所述河岸或所述建成区之上的第端(24)以及悬于桥梁施工区(14)之上的第二端(26),-施工步骤,其中,桥墩构件和桥面构件(10)通过第个升降装置和第二个升降装置(18、2
AbstractList A method for building a bridge, said bridge (4) comprising piers (6) and at least one deck (8), the method comprising: - a cantilever step, wherein a girder (16) is set in a cantilevered position relative to a bank or to a constructed zone (12) of the bridge so that the girder comprises a first end (24) overhanging the bank or the constructed zone, and a second end (26) overhanging a construction zone (14) of the bridge, - a construction step, wherein pier elements and deck elements (10) are installed in said construction zone (14) via a first and a second lifting devices (18, 20) mounted movable on the girder (16) between the first and second ends (24, 26). The first and second lifting devices (18, 20) cross one another along the girder during the cantilever step and/or during the construction step. Associated bridge-building apparatus. 种建造桥梁的方法,所述桥梁(4)包括桥墩(6)以及至少个桥面(8),该方法包括:-悬臂步骤,其中,把主梁(16)设置在与河岸或桥梁建成区(12)相对的悬臂位置,所以主梁包括悬于所述河岸或所述建成区之上的第端(24)以及悬于桥梁施工区(14)之上的第二端(26),-施工步骤,其中,桥墩构件和桥面构件(10)通过第个升降装置和第二个升降装置(18、2
Author BERMINGHAM PATRICK D
GABALDO STEFANO L
MELLIER ERIK
LE TREUT BRICE
Author_xml – fullname: GABALDO STEFANO L
– fullname: BERMINGHAM PATRICK D
– fullname: LE TREUT BRICE
– fullname: MELLIER ERIK
BookMark eNrjYmDJy89L5WSw8k0tychPUUjLL1JIKs3MScnMS1dIVEgqykxJT1VIzEuBMnURkgUFiUWJJaXFPAysaYk5xam8UJqbQdHNNcTZQze1ID8-tbggMTk1L7Uk3tnP0MDM1NzExMTS0ZgYNQBNdDB_
ContentType Patent
DBID EVB
DatabaseName esp@cenet
DatabaseTitleList
Database_xml – sequence: 1
  dbid: EVB
  name: esp@cenet
  url: http://worldwide.espacenet.com/singleLineSearch?locale=en_EP
  sourceTypes: Open Access Repository
DeliveryMethod fulltext_linktorsrc
Discipline Medicine
Chemistry
Sciences
DocumentTitleAlternate 建造桥梁的方法及建造桥梁的装置
ExternalDocumentID CN106574449A
GroupedDBID EVB
ID FETCH-epo_espacenet_CN106574449A3
IEDL.DBID EVB
IngestDate Fri Jul 19 15:01:14 EDT 2024
IsOpenAccess true
IsPeerReviewed false
IsScholarly false
Language Chinese
English
LinkModel DirectLink
MergedId FETCHMERGED-epo_espacenet_CN106574449A3
Notes Application Number: CN201480079994
OpenAccessLink https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20170419&DB=EPODOC&CC=CN&NR=106574449A
ParticipantIDs epo_espacenet_CN106574449A
PublicationCentury 2000
PublicationDate 20170419
PublicationDateYYYYMMDD 2017-04-19
PublicationDate_xml – month: 04
  year: 2017
  text: 20170419
  day: 19
PublicationDecade 2010
PublicationYear 2017
RelatedCompanies SOLETANCHE FREYSSINET
RelatedCompanies_xml – name: SOLETANCHE FREYSSINET
Score 3.2024412
Snippet A method for building a bridge, said bridge (4) comprising piers (6) and at least one deck (8), the method comprising: - a cantilever step, wherein a girder...
SourceID epo
SourceType Open Access Repository
SubjectTerms ASSEMBLY OF BRIDGES
CONSTRUCTION OF BRIDGES
CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
FIXED CONSTRUCTIONS
OR VIADUCTS
Title Method for building a bridge and bridge-building apparatus
URI https://worldwide.espacenet.com/publicationDetails/biblio?FT=D&date=20170419&DB=EPODOC&locale=&CC=CN&NR=106574449A
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV3dS8MwED_mFPVNp6LzgwjSt2Bn03YVirh0ZQjthkzZ20ibDPWhK7ZD8K_3Gjvri74dCRyXg8vd5XK_A7jCmNhW6IpoX5kWZQvPpgL9FJWiL6wb0xaORtePYmf0xB5m9qwFb-teGI0T-qHBEdGiUrT3Ut_XefOIFei_lcV18opLy7tw6gdGnR33XJOhBQYDfzgZB2NucO7z2IgfMdZ1bJcx5t1vwCaG0a5O2p4HVVdK_tulhHuwNUFuWbkPrc-XDuzw9eS1DmxHdcEbydr2igO4jfSwZ4JRJknqYdZEkO-OKyIyWZO02cw1sPeqOITLcDjlI4pCzH9OPOdxI691BO1smaljIAtppkpKZrtphRwvvFQqC7NhVKuZSCZPoPs3n-5_m6ewW2mvKpP0vDNol-8rdY7etkwutJq-ACNmg84
link.rule.ids 230,309,783,888,25577,76883
linkProvider European Patent Office
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV3dS8NADA9zivNNp6Lzq4L0rdjZ65dQxF1Xqq7dkCp7G9deh_rQFdsh-Nebnp31Rd_CHYRcIJfkcvkF4AJjYj1FV6RYqaopZG7rCkM_pXBmMe1K1Zkh0PWD0PCfyP1Un7bgbdULI3BCPwQ4IlpUgvZeivs6bx6xXPG3sriMX3FpceNFjivX2XHfVAlaoDtwhpOxO6YypQ4N5fARY11DNwkh9u0arGOIbYlU6XlQdaXkv12Ktw0bE-SWlTvQ-nzpQoeuJq91YTOoC95I1rZX7MJ1IIY9SxhlSnE9zFpi0nfHlcQyXpNKs5kLYO9lsQfn3jCivoJCzH5OPKNhI6-2D-1skaUHIM25mqScE91MKuR4Zic81TAbRrWqMSf8EHp_8-n9t3kGHT8KRrPRXfhwBFuVJquSSd8-hnb5vkxP0POW8alQ2Rd5SIa-
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Apatent&rft.title=Method+for+building+a+bridge+and+bridge-building+apparatus&rft.inventor=GABALDO+STEFANO+L&rft.inventor=BERMINGHAM+PATRICK+D&rft.inventor=LE+TREUT+BRICE&rft.inventor=MELLIER+ERIK&rft.date=2017-04-19&rft.externalDBID=A&rft.externalDocID=CN106574449A