Approximability results for the resource-constrained project scheduling problem with a single type of resources

In this paper, we consider the well-known resource-constrained project scheduling problem. We give some arguments that already a special case of this problem with a single type of resources is not approximable in polynomial time with an approximation ratio bounded by a constant. We prove that there...

Full description

Saved in:
Bibliographic Details
Published inAnnals of operations research Vol. 213; no. 1; pp. 115 - 130
Main Authors Gafarov, Evgeny R., Lazarev, Alexander A., Werner, Frank
Format Journal Article
LanguageEnglish
Published Boston Springer US 01.02.2014
Springer
Springer Nature B.V
Subjects
Online AccessGet full text

Cover

Loading…
More Information
Summary:In this paper, we consider the well-known resource-constrained project scheduling problem. We give some arguments that already a special case of this problem with a single type of resources is not approximable in polynomial time with an approximation ratio bounded by a constant. We prove that there exist instances for which the optimal makespan values for the non-preemptive and the preemptive problems have a ratio of O (log n ), where n is the number of jobs. This means that there exist instances for which the lower bound of Mingozzi et al. has a bad relative error of O (log n ), and the calculation of this bound is an NP-hard problem. In addition, we give a proof that there exists a type of instances for which known approximation algorithms with polynomial time complexity have an approximation ratio of at least equal to , and known lower bounds have a relative error of at least equal to O (log n ). This type of instances corresponds to the single machine parallel-batch scheduling problem 1| p − batch , b =∞| C max .