Development of Innovative Integrated Last Planner System (ILPS)

Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction (LC) and improving construction productivity. The past 25 years have witnessed the sequential development of LPS but still, the construction industry is unable to utilize its full pot...

Full description

Saved in:
Bibliographic Details
Published inInternational journal of civil engineering (Tehran. Online) Vol. 18; no. 6; pp. 701 - 715
Main Authors Aslam, Mughees, Gao, Zhili, Smith, Gary
Format Journal Article
LanguageEnglish
Published Cham Springer International Publishing 01.06.2020
Subjects
Online AccessGet full text

Cover

Loading…
Abstract Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction (LC) and improving construction productivity. The past 25 years have witnessed the sequential development of LPS but still, the construction industry is unable to utilize its full potentials. It was reported that users of LPS were only able to achieve 70% of their weekly assignments with much potential to perform better. Considering it is a complete lean construction tool, LPS is mostly implemented in isolation, thereby exposing many areas that are overlooked and poorly managed. In this study, an effort has been made in developing strategies to overcome LPS implementation challenges by integrating LPS with other available lean tools and techniques. A systematic literature review is carried out, followed by a conceptual development of findings and theories into a robust integrated LPS implementation model. Thirteen (13) major shortcomings in implementing LPS and sixteen (16) lean tools to overcome these shortcomings are identified. Presently, LPS is managed as a single entity. However, due to its vast diversity, all of its stages should be managed independently. In this study, lean tools are integrated within LPS stages to develop the innovative integrated last planner system (ILPS), allowing the management of LPS stages independently. Additionally, a guideline for sequential amalgamation of LPS with the lean tools at different stages is presented to smoothen the ILPS implementation process. The ILPS will facilitate the construction industry in utilizing LPS to its fullest potential. This newly developed ILPS will help the lean practitioners in increasing construction productivity and reducing cost and time.
AbstractList Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction (LC) and improving construction productivity. The past 25 years have witnessed the sequential development of LPS but still, the construction industry is unable to utilize its full potentials. It was reported that users of LPS were only able to achieve 70% of their weekly assignments with much potential to perform better. Considering it is a complete lean construction tool, LPS is mostly implemented in isolation, thereby exposing many areas that are overlooked and poorly managed. In this study, an effort has been made in developing strategies to overcome LPS implementation challenges by integrating LPS with other available lean tools and techniques. A systematic literature review is carried out, followed by a conceptual development of findings and theories into a robust integrated LPS implementation model. Thirteen (13) major shortcomings in implementing LPS and sixteen (16) lean tools to overcome these shortcomings are identified. Presently, LPS is managed as a single entity. However, due to its vast diversity, all of its stages should be managed independently. In this study, lean tools are integrated within LPS stages to develop the innovative integrated last planner system (ILPS), allowing the management of LPS stages independently. Additionally, a guideline for sequential amalgamation of LPS with the lean tools at different stages is presented to smoothen the ILPS implementation process. The ILPS will facilitate the construction industry in utilizing LPS to its fullest potential. This newly developed ILPS will help the lean practitioners in increasing construction productivity and reducing cost and time.
Author Aslam, Mughees
Gao, Zhili
Smith, Gary
Author_xml – sequence: 1
  givenname: Mughees
  surname: Aslam
  fullname: Aslam, Mughees
  organization: Department of Construction Management and Engineering, North Dakota State University, Department of Construction Engineering and Management, National University of Science and Technology
– sequence: 2
  givenname: Zhili
  orcidid: 0000-0002-7623-9638
  surname: Gao
  fullname: Gao, Zhili
  email: jerry.gao@ndsu.edu
  organization: Department of Construction Management and Engineering, North Dakota State University
– sequence: 3
  givenname: Gary
  surname: Smith
  fullname: Smith, Gary
  organization: Department of Construction Management and Engineering, North Dakota State University
BookMark eNp9kD1PwzAQhi1UJErpH2DKCIPhknM-PCFUvipFolJhtpzkXKVKnco2lfrvCYSJodPdcM_pfZ9LNrG9JcauY7iLAfJ7L0BKySEBDpCC4PKMTRMskGORiwmbxjmmHNIkuWBz77cAkMgMEdMpe3iiA3X9fkc2RL2Jltb2Bx3aAw1roI3TgZqo1D5Eq05bSy5aH32gXXSzLFfr2yt2bnTnaf43Z-zz5flj8cbL99fl4rHkNWYicKGpymoUIiOABhGkaUSTV4XIkyLOKllhTtCkCDHURhCa2miKta6wEalAnLFi_Fu73ntHRtVtGHL2NjjddioG9eNCjS7U4EL9ulByQJN_6N61O-2OpyEcIT8c2w05te2_nB0qnqK-AXhzcqo
CitedBy_id crossref_primary_10_3390_buildings13102507
crossref_primary_10_1108_IJLSS_06_2020_0071
crossref_primary_10_1061_JCEMD4_COENG_14420
crossref_primary_10_3390_su16051857
crossref_primary_10_1080_10429247_2023_2187608
crossref_primary_10_1080_09537287_2020_1859151
crossref_primary_10_1061_JCEMD4_COENG_13427
crossref_primary_10_1016_j_techfore_2023_122545
Cites_doi 10.1061/(ASCE)CO.1943-7862.0001468
10.1007/978-981-15-0802-8_163
10.1061/(ASCE)CO.1943-7862.0001691
10.4067/S0718-50732008000100003
10.1016/j.buildenv.2018.10.051
10.1061/(ASCE)CO.1943-7862.0000975
10.1007/s12205-015-1412-y
10.1061/(ASCE)0733-9364(2006)132:3(291)
10.1080/15623599.2018.1484861
10.1061/(ASCE)ME.1943-5479.0000699
10.1061/(ASCE)ME.1943-5479.0000056
10.2174/1874836801812010389
10.1016/j.ijproman.2014.01.002
10.1108/ECAM-08-2017-0162
10.1061/(ASCE)CO.1943-7862.0000606
10.1016/j.aej.2013.04.008
10.1108/CI-01-2016-0002
10.24928/2018/0433
10.4324/9780080491080-24
10.1061/9780784413135.003
10.5592/otmcj.2013.3.2
10.60164/e2i9e2h1d
ContentType Journal Article
Copyright Iran University of Science and Technology 2020
Copyright_xml – notice: Iran University of Science and Technology 2020
DBID AAYXX
CITATION
DOI 10.1007/s40999-020-00504-9
DatabaseName CrossRef
DatabaseTitle CrossRef
DatabaseTitleList
DeliveryMethod fulltext_linktorsrc
Discipline Engineering
EISSN 2383-3874
EndPage 715
ExternalDocumentID 10_1007_s40999_020_00504_9
GroupedDBID -EM
0R~
2XV
406
AACDK
AAHNG
AAIAL
AAJBT
AANZL
AARHV
AASML
AATNV
AATVU
AAUYE
AAYQN
AAYTO
ABAKF
ABDZT
ABECU
ABFTV
ABJNI
ABJOX
ABKCH
ABMQK
ABQBU
ABTEG
ABTKH
ABTMW
ABXPI
ACAOD
ACDTI
ACGFS
ACHSB
ACMLO
ACOKC
ACPIV
ACZOJ
ADHHG
ADKNI
ADURQ
ADYFF
ADZKW
AEBTG
AEFQL
AEJHL
AEJRE
AEMSY
AENEX
AEOHA
AEPYU
AESKC
AEVLU
AEXYK
AFBBN
AFQWF
AFZKB
AGDGC
AGMZJ
AGQEE
AGQMX
AGRTI
AHKAY
AHSBF
AIAKS
AIGIU
AILAN
AITGF
AJRNO
AJZVZ
ALFXC
ALMA_UNASSIGNED_HOLDINGS
AMKLP
AMXSW
AMYLF
AMYQR
ASPBG
AVWKF
AXYYD
BGNMA
DNIVK
DPUIP
EBLON
EBS
EIOEI
EJD
FERAY
FIGPU
FINBP
FNLPD
FSGXE
GGCAI
GJIRD
IAO
IKXTQ
ISR
ITC
IWAJR
J-C
JZLTJ
KOV
LLZTM
M4Y
NPVJJ
NQJWS
NU0
O9J
PT4
RLLFE
ROL
RSV
SJYHP
SNE
SNPRN
SNX
SOHCF
SOJ
SPISZ
SRMVM
SSLCW
STPWE
TSG
UG4
UOJIU
UTJUX
UZXMN
VFIZW
ZMTXR
AAYXX
ABBRH
ABDBE
ABFSG
ACSTC
AEZWR
AFDZB
AFHIU
AFOHR
AHPBZ
AHWEU
AIXLP
ATHPR
AYFIA
CITATION
ID FETCH-LOGICAL-c364t-4aeb6c3446e00d3309fd4d7b8472816b9b37e0d53010cf4e3fcfae1aab3d45433
ISSN 1735-0522
IngestDate Tue Jul 01 01:28:53 EDT 2025
Thu Apr 24 23:13:17 EDT 2025
Fri Feb 21 02:36:24 EST 2025
IsPeerReviewed false
IsScholarly true
Issue 6
Keywords Visualization
Shortcomings
Look-ahead planning
Lean tools and techniques
Constraint analysis
Integrated last planner system (ILPS)
Language English
LinkModel OpenURL
MergedId FETCHMERGED-LOGICAL-c364t-4aeb6c3446e00d3309fd4d7b8472816b9b37e0d53010cf4e3fcfae1aab3d45433
ORCID 0000-0002-7623-9638
PageCount 15
ParticipantIDs crossref_citationtrail_10_1007_s40999_020_00504_9
crossref_primary_10_1007_s40999_020_00504_9
springer_journals_10_1007_s40999_020_00504_9
ProviderPackageCode CITATION
AAYXX
PublicationCentury 2000
PublicationDate 20200600
2020-06-00
PublicationDateYYYYMMDD 2020-06-01
PublicationDate_xml – month: 6
  year: 2020
  text: 20200600
PublicationDecade 2020
PublicationPlace Cham
PublicationPlace_xml – name: Cham
PublicationTitle International journal of civil engineering (Tehran. Online)
PublicationTitleAbbrev Int J Civ Eng
PublicationYear 2020
Publisher Springer International Publishing
Publisher_xml – name: Springer International Publishing
References Liu, Ballard, Ibbs (CR40) 2010; 27
CR19
CR18
CR17
Agbulos, Mohamed, Al-Hussein, AbouRizk, Roesch (CR30) 2006; 132
CR39
Brittle, Gaedicke, Akhavian (CR2) 2018; 16
CR38
CR15
CR37
CR14
Ballard, Howell, Alarcón (CR31) 1994
CR36
Aboseif, Khallaf (CR23) 2020
CR12
CR34
Aziz, Hafez (CR32) 2013; 52
CR33
Perez, Ghosh (CR11) 2018; 25
Alarcón, Diethelm, Rojo, Calderón (CR13) 2011; 23
Khanh, Kim (CR16) 2016; 20
CR6
CR5
Gao, Low (CR7) 2014; 32
El-Sabek, McCabe (CR1) 2018; 144
CR29
CR28
CR9
CR27
Daniel, Pasquire, Dickens (CR8) 2019; 35
Lagos, Herrera, Alarcón (CR21) 2019; 145
CR26
Tayeh, Al Hallaq, Al Faqawi, Alaloul, Kim (CR10) 2018; 12
CR25
Babalola, Ibem, Ezema (CR35) 2018; 148
CR47
CR46
CR45
CR44
CR43
CR20
CR42
CR41
Zaeri, Rotimi, Hosseini, Cox (CR22) 2017; 17
Abusalem (CR24) 2018
Fernandez-Solis (CR3) 2013; 139
Priven, Sacks (CR4) 2015; 141
504_CR19
504_CR18
504_CR17
504_CR39
504_CR38
S Gao (504_CR7) 2014; 32
504_CR15
504_CR37
BA Tayeh (504_CR10) 2018; 12
504_CR14
504_CR36
AM Perez (504_CR11) 2018; 25
A Agbulos (504_CR30) 2006; 132
504_CR12
504_CR34
504_CR33
LM El-Sabek (504_CR1) 2018; 144
O Abusalem (504_CR24) 2018
RF Aziz (504_CR32) 2013; 52
JL Fernandez-Solis (504_CR3) 2013; 139
G Ballard (504_CR31) 1994
504_CR29
504_CR28
M Liu (504_CR40) 2010; 27
504_CR27
504_CR26
504_CR25
504_CR47
P Brittle (504_CR2) 2018; 16
CI Lagos (504_CR21) 2019; 145
504_CR46
504_CR45
504_CR44
504_CR43
504_CR20
504_CR42
504_CR41
F Zaeri (504_CR22) 2017; 17
HD Khanh (504_CR16) 2016; 20
LF Alarcón (504_CR13) 2011; 23
E Aboseif (504_CR23) 2020
O Babalola (504_CR35) 2018; 148
504_CR6
504_CR5
V Priven (504_CR4) 2015; 141
EI Daniel (504_CR8) 2019; 35
504_CR9
References_xml – ident: CR45
– volume: 144
  start-page: 04018022
  issue: 5
  year: 2018
  ident: CR1
  article-title: Framework for managing integration challenges of last planner system in IMPs
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0001468
– ident: CR18
– ident: CR43
– start-page: 1019
  year: 2020
  end-page: 1024
  ident: CR23
  article-title: A framework for last planner system implementation in Egypt
  publication-title: CIGOS, 2019 innovation for sustainable infrastructure
  doi: 10.1007/978-981-15-0802-8_163
– ident: CR47
– volume: 145
  start-page: 04019055
  issue: 10
  year: 2019
  ident: CR21
  article-title: Assessing the impacts of an IT LPS support system on schedule accomplishment in construction projects
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0001691
– volume: 23
  start-page: 26
  issue: 1
  year: 2011
  end-page: 33
  ident: CR13
  article-title: Assessing the impacts of implementing lean construction
  publication-title: Rev Ing Constr
  doi: 10.4067/S0718-50732008000100003
– ident: CR14
– ident: CR39
– ident: CR37
– ident: CR12
– volume: 148
  start-page: 34
  year: 2018
  end-page: 43
  ident: CR35
  article-title: Implementation of lean practices in the construction industry: a systematic review
  publication-title: Build Environ
  doi: 10.1016/j.buildenv.2018.10.051
– ident: CR33
– volume: 141
  start-page: 04015006
  issue: 6
  year: 2015
  ident: CR4
  article-title: Effects of the last planner system on social networks among construction trade crews
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0000975
– start-page: 101
  year: 1994
  end-page: 110
  ident: CR31
  article-title: Implementing lean construction: stabilizing work flow
  publication-title: Lean construction in 1997
– volume: 20
  start-page: 1
  issue: 1
  year: 2016
  end-page: 11
  ident: CR16
  article-title: A survey on production planning system in construction projects based on last planner system
  publication-title: KSCE J Civ Eng
  doi: 10.1007/s12205-015-1412-y
– ident: CR6
– ident: CR29
– volume: 132
  start-page: 291
  year: 2006
  end-page: 299
  ident: CR30
  article-title: Application of lean concepts and simulation analysis to improve efficiency of drainage operations maintenance crews
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)0733-9364(2006)132:3(291)
– year: 2018
  ident: CR24
  article-title: Towards last planner system implementation in Gaza Strip, Palestine
  publication-title: Int J Constr Manag
  doi: 10.1080/15623599.2018.1484861
– ident: CR25
– volume: 35
  start-page: 04019018
  issue: 5
  year: 2019
  ident: CR8
  article-title: Development of approach to support construction stakeholders in implementation of the last planner system
  publication-title: J Manag Eng
  doi: 10.1061/(ASCE)ME.1943-5479.0000699
– ident: CR27
– ident: CR42
– ident: CR46
– ident: CR19
– ident: CR44
– volume: 27
  start-page: 236
  issue: 4
  year: 2010
  end-page: 242
  ident: CR40
  article-title: Work flow variation and labor productivity: case study
  publication-title: J Manag Eng
  doi: 10.1061/(ASCE)ME.1943-5479.0000056
– ident: CR15
– ident: CR38
– volume: 16
  start-page: 59
  issue: 1
  year: 2018
  ident: CR2
  article-title: Perspective of the last planner: effectiveness of the traditional critical path method in comparison with the last planner system
  publication-title: J Supply Chain Oper Manag
– volume: 12
  start-page: 1
  year: 2018
  ident: CR10
  article-title: success factors and barriers of last planner system implementation in the Gaza Strip construction industry
  publication-title: Open Constr Build Technol J
  doi: 10.2174/1874836801812010389
– ident: CR17
– volume: 32
  start-page: 1260
  issue: 7
  year: 2014
  end-page: 1272
  ident: CR7
  article-title: The last planner system in China's construction industry—a SWOT analysis on implementation
  publication-title: Int J Project Manag
  doi: 10.1016/j.ijproman.2014.01.002
– volume: 25
  start-page: 1110
  issue: 9
  year: 2018
  end-page: 1126
  ident: CR11
  article-title: Barriers faced by new-adopter of last planner system®: a case study
  publication-title: Eng Constr Archit Manag
  doi: 10.1108/ECAM-08-2017-0162
– ident: CR9
– ident: CR34
– ident: CR36
– volume: 139
  start-page: 354
  issue: 4
  year: 2013
  end-page: 360
  ident: CR3
  article-title: Survey of motivations, benefits, and implementation challenges of last planner system users
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0000606
– ident: CR5
– ident: CR28
– ident: CR41
– ident: CR26
– volume: 52
  start-page: 679
  issue: 4
  year: 2013
  end-page: 695
  ident: CR32
  article-title: Applying lean thinking in construction and performance improvement
  publication-title: Alex Eng J
  doi: 10.1016/j.aej.2013.04.008
– ident: CR20
– volume: 17
  start-page: 324
  issue: 3
  year: 2017
  end-page: 339
  ident: CR22
  article-title: Implementation of the LPS using an excel spreadsheet: a case study from the New Zealand construction industry
  publication-title: Constr Innov
  doi: 10.1108/CI-01-2016-0002
– ident: 504_CR12
– volume: 139
  start-page: 354
  issue: 4
  year: 2013
  ident: 504_CR3
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0000606
– ident: 504_CR37
– ident: 504_CR39
– volume: 25
  start-page: 1110
  issue: 9
  year: 2018
  ident: 504_CR11
  publication-title: Eng Constr Archit Manag
  doi: 10.1108/ECAM-08-2017-0162
– volume: 145
  start-page: 04019055
  issue: 10
  year: 2019
  ident: 504_CR21
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0001691
– volume: 27
  start-page: 236
  issue: 4
  year: 2010
  ident: 504_CR40
  publication-title: J Manag Eng
  doi: 10.1061/(ASCE)ME.1943-5479.0000056
– ident: 504_CR18
– ident: 504_CR14
– volume: 23
  start-page: 26
  issue: 1
  year: 2011
  ident: 504_CR13
  publication-title: Rev Ing Constr
  doi: 10.4067/S0718-50732008000100003
– volume: 52
  start-page: 679
  issue: 4
  year: 2013
  ident: 504_CR32
  publication-title: Alex Eng J
  doi: 10.1016/j.aej.2013.04.008
– start-page: 1019
  volume-title: CIGOS, 2019 innovation for sustainable infrastructure
  year: 2020
  ident: 504_CR23
  doi: 10.1007/978-981-15-0802-8_163
– ident: 504_CR25
  doi: 10.24928/2018/0433
– ident: 504_CR27
– ident: 504_CR46
– ident: 504_CR5
– ident: 504_CR29
– ident: 504_CR44
– ident: 504_CR42
– ident: 504_CR33
  doi: 10.4324/9780080491080-24
– volume: 148
  start-page: 34
  year: 2018
  ident: 504_CR35
  publication-title: Build Environ
  doi: 10.1016/j.buildenv.2018.10.051
– volume: 12
  start-page: 1
  year: 2018
  ident: 504_CR10
  publication-title: Open Constr Build Technol J
  doi: 10.2174/1874836801812010389
– volume: 20
  start-page: 1
  issue: 1
  year: 2016
  ident: 504_CR16
  publication-title: KSCE J Civ Eng
  doi: 10.1007/s12205-015-1412-y
– ident: 504_CR9
– ident: 504_CR36
– year: 2018
  ident: 504_CR24
  publication-title: Int J Constr Manag
  doi: 10.1080/15623599.2018.1484861
– ident: 504_CR34
– volume: 35
  start-page: 04019018
  issue: 5
  year: 2019
  ident: 504_CR8
  publication-title: J Manag Eng
  doi: 10.1061/(ASCE)ME.1943-5479.0000699
– start-page: 101
  volume-title: Lean construction in 1997
  year: 1994
  ident: 504_CR31
– ident: 504_CR17
– ident: 504_CR15
– ident: 504_CR47
– volume: 144
  start-page: 04018022
  issue: 5
  year: 2018
  ident: 504_CR1
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0001468
– ident: 504_CR19
  doi: 10.1061/9780784413135.003
– volume: 141
  start-page: 04015006
  issue: 6
  year: 2015
  ident: 504_CR4
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)CO.1943-7862.0000975
– ident: 504_CR26
– ident: 504_CR28
  doi: 10.5592/otmcj.2013.3.2
– ident: 504_CR45
– ident: 504_CR38
  doi: 10.60164/e2i9e2h1d
– volume: 132
  start-page: 291
  year: 2006
  ident: 504_CR30
  publication-title: J Constr Eng Manag
  doi: 10.1061/(ASCE)0733-9364(2006)132:3(291)
– ident: 504_CR6
– ident: 504_CR41
– ident: 504_CR43
– volume: 16
  start-page: 59
  issue: 1
  year: 2018
  ident: 504_CR2
  publication-title: J Supply Chain Oper Manag
– ident: 504_CR20
– volume: 32
  start-page: 1260
  issue: 7
  year: 2014
  ident: 504_CR7
  publication-title: Int J Project Manag
  doi: 10.1016/j.ijproman.2014.01.002
– volume: 17
  start-page: 324
  issue: 3
  year: 2017
  ident: 504_CR22
  publication-title: Constr Innov
  doi: 10.1108/CI-01-2016-0002
SSID ssj0002963335
ssib031263548
ssib045315334
Score 2.2194757
Snippet Last planner system (LPS) has been recognized as one of the most formidable tools for implementing lean construction (LC) and improving construction...
SourceID crossref
springer
SourceType Enrichment Source
Index Database
Publisher
StartPage 701
SubjectTerms Civil Engineering
Engineering
Research Paper
Title Development of Innovative Integrated Last Planner System (ILPS)
URI https://link.springer.com/article/10.1007/s40999-020-00504-9
Volume 18
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV1La9wwEBbb5NIeQp806QMdemjZepEtyZZPJSl5UJJQ6AZCL0ay5CYlbErWm0NP_ekdPWw52SQ0vRgj7MFoPo9Go5lvEHpnYBthKCeJaJRKmM5UooQkCSeKK1YyLVy84-Aw3ztiX4758Wj0Z5C1tGjVpP59Y13J_2gVxkCvtkr2HprthcIA3IN-4Qoahus_6XiQ8eNLQnyH00ufD-lYIPR4X85b35vIXASCcudW7n_91oUBfsZ09hgdHHBK1KeXp2djE6kLrYCpOYF1bjIekpV67HQoO1j8ODExR3FXurDsdxvCWQrs7MqQjxwiEBmJmVLBaBaUJ4T7-uKJcWPgCVDL28tutrTXzGYRxPkVuPAFnkvG3edzzBlxzAn2OwgnLCnjUtYd319b4fq8w56j2cmoQEblZFTlA7SawUYDLOXq5s7W1mFnk2hq2XrilpGBzbLVy30cLwMLRl0f134aQm2Wq9Bc-tir_s_Vw3fn00wfo7WwGcGbHllP0MjMnqJHA4rKZ-jTAGP4vMERYzhiDFuM4YAx7DGG31uEfXiOjna2p5_3ktB0I6lpztqESaPymjKWG0I0paRsNNOFAi8mE2muSkULQzSHhYHUDTO0qRtpUikV1YwzSl-gldn5zLxEONVCFrluZJkLJkotanixzkVjlGjSVK2jtJuKqg6M9LYxyll1u57W0bh_55fnY7nz6Y_dDFfhr5nf8fjGvYS_Qg_j3_AarbQXC_MGPNRWvQ0g-gvjqoRd
linkProvider Library Specific Holdings
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Development+of+Innovative+Integrated+Last+Planner+System+%28ILPS%29&rft.jtitle=International+journal+of+civil+engineering+%28Tehran.+Online%29&rft.au=Aslam%2C+Mughees&rft.au=Gao%2C+Zhili&rft.au=Smith%2C+Gary&rft.date=2020-06-01&rft.issn=1735-0522&rft.eissn=2383-3874&rft.volume=18&rft.issue=6&rft.spage=701&rft.epage=715&rft_id=info:doi/10.1007%2Fs40999-020-00504-9&rft.externalDBID=n%2Fa&rft.externalDocID=10_1007_s40999_020_00504_9
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=1735-0522&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=1735-0522&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=1735-0522&client=summon