Project management challenges for post-disaster reconstruction projects in Angola: a public sector perspective

PurposeDespite the extensive research on post-disaster reconstruction projects (PDRP), there is a paucity of studies that examine critical challenges for the project practices in post-war-developing countries, particularly, Africa. The purpose of this research is to investigate the key project manag...

Full description

Saved in:
Bibliographic Details
Published inInternational journal of managing projects in business Vol. 14; no. 3; pp. 767 - 787
Main Authors Sospeter, Nyamagere Gladys, Rwelamila, Pantaleo M.D., Gimbi, Joaqium
Format Journal Article
LanguageEnglish
Published Bingley Emerald Publishing Limited 06.04.2021
Emerald Group Publishing Limited
Subjects
Online AccessGet full text

Cover

Loading…
Abstract PurposeDespite the extensive research on post-disaster reconstruction projects (PDRP), there is a paucity of studies that examine critical challenges for the project practices in post-war-developing countries, particularly, Africa. The purpose of this research is to investigate the key project management challenges impacting the post-disaster reconstruction projects (PDRP) during the construction and planning stages in Angola, with an aim to fill the knowledge gap.Design/methodology/approachThe primary data was collected from 130 project management practitioners working with planning, provincial government organisations including consultants, and contractors within the Angolan public sectors organisations. Response data was subjected to descriptive statistics, mean scores, and inferential statistics (One sample t-tests) and Kendall's concordance.FindingsThe descriptive and empirical analysis demonstrated a disparity of the ranking of the 21challenges affecting the PDRP among the groups; with statistically significant differences amongst the 10 challenges. Based on the overall sample, 6 out of 10 critical challenges are between (24–25) levels of agreement close to the mean. The results of the mean score ranking indicate that “working with poor or restricted access to location”, “project culture that fits the needs of local people”; “improving the capacity of local government”, “minimizing the negative effects of local people” and “relocation issues by establishing property rights during the reconstruction project” were the five critical challenges to managing PDRP whereas “improving information and communication processes”, “securing adequate resources (material and machinery)”, “dealing with rising costs of materials and labour” were considered to be the least critical.Research limitations/implicationsThe study was restricted to one province and Country (out of 18) namely, Luanda, Angola. Therefore, the findings may not be generalized to public sector organisations operating in different countries with different contexts, political settings and disaster complexities.Practical implicationsThe establishment of challenges in PDRPs helps the key stakeholders by providing the foundation to project teams to address the challenges during planning and construction stages, and thus improving project delivery in the future. Understanding the uniqueness of PDRPs and interdependency of project management from the implementing organization is of particular value for the managers of future projects and other decision-makers, especially in the emerging countries. Moreover, the findings could be used to reflect on the need to formulate policies appropriate to post disaster environments, which among other issues could address building policies, which could include land ownership regulations and procedures together with property rights.Originality/valueThis study contributes to the body of knowledge on the subject within a previously unexplored post-war context with a focus on public organizations perspective. The study provides insights on the challenges affecting the post-disaster reconstruction across the Angolan public sector.
AbstractList PurposeDespite the extensive research on post-disaster reconstruction projects (PDRP), there is a paucity of studies that examine critical challenges for the project practices in post-war-developing countries, particularly, Africa. The purpose of this research is to investigate the key project management challenges impacting the post-disaster reconstruction projects (PDRP) during the construction and planning stages in Angola, with an aim to fill the knowledge gap.Design/methodology/approachThe primary data was collected from 130 project management practitioners working with planning, provincial government organisations including consultants, and contractors within the Angolan public sectors organisations. Response data was subjected to descriptive statistics, mean scores, and inferential statistics (One sample t-tests) and Kendall's concordance.FindingsThe descriptive and empirical analysis demonstrated a disparity of the ranking of the 21challenges affecting the PDRP among the groups; with statistically significant differences amongst the 10 challenges. Based on the overall sample, 6 out of 10 critical challenges are between (24–25) levels of agreement close to the mean. The results of the mean score ranking indicate that “working with poor or restricted access to location”, “project culture that fits the needs of local people”; “improving the capacity of local government”, “minimizing the negative effects of local people” and “relocation issues by establishing property rights during the reconstruction project” were the five critical challenges to managing PDRP whereas “improving information and communication processes”, “securing adequate resources (material and machinery)”, “dealing with rising costs of materials and labour” were considered to be the least critical.Research limitations/implicationsThe study was restricted to one province and Country (out of 18) namely, Luanda, Angola. Therefore, the findings may not be generalized to public sector organisations operating in different countries with different contexts, political settings and disaster complexities.Practical implicationsThe establishment of challenges in PDRPs helps the key stakeholders by providing the foundation to project teams to address the challenges during planning and construction stages, and thus improving project delivery in the future. Understanding the uniqueness of PDRPs and interdependency of project management from the implementing organization is of particular value for the managers of future projects and other decision-makers, especially in the emerging countries. Moreover, the findings could be used to reflect on the need to formulate policies appropriate to post disaster environments, which among other issues could address building policies, which could include land ownership regulations and procedures together with property rights.Originality/valueThis study contributes to the body of knowledge on the subject within a previously unexplored post-war context with a focus on public organizations perspective. The study provides insights on the challenges affecting the post-disaster reconstruction across the Angolan public sector.
Author Sospeter, Nyamagere Gladys
Gimbi, Joaqium
Rwelamila, Pantaleo M.D.
Author_xml – sequence: 1
  givenname: Nyamagere Gladys
  surname: Sospeter
  fullname: Sospeter, Nyamagere Gladys
  email: nyamagere@yahoo.com
– sequence: 2
  givenname: Pantaleo M.D.
  orcidid: 0000-0002-1794-7255
  surname: Rwelamila
  fullname: Rwelamila, Pantaleo M.D.
  email: Rwelapmd@unisa.ac.za
– sequence: 3
  givenname: Joaqium
  surname: Gimbi
  fullname: Gimbi, Joaqium
  email: joaqgimbi@hotmail.com
BookMark eNp9kV1LwzAUhoNMcJv-Aa8CXleTpm1S7-bwYzJxF3od0vR0dnRJTVLBf29rRVDEq_PCyXNy8mSGJsYaQOiUknNKibhY3T9sriLCopjEJCJE8AM0pTxlkWAim3xnLo7QzPsdIVmeUDpFZuPsDnTAe2XUFvZgAtYvqmnAbMHjyjrcWh-isvbKB3DYgbbGB9fpUFuD2xH3uDZ4Yba2UZdY4bYrmlpj33eGAeB828f6DY7RYaUaDydfdY6eb66flnfR-vF2tVysI80oD5GiKcsopEKQTKScVwWPFQeAkmgBwAloUsQ6yTllDFLQuSiTigPVmhU6z9gcnY1z-_1eO_BB7mznTH-ljFOWUMZ5L2SOxHhKO-u9g0rqOqjhXcGpupGUyMGu_LQrCZODXTnY7dH4F9q6eq_c-_8QHaHes1NN-Tfz4xvZBynMkGQ
CitedBy_id crossref_primary_10_1080_15578771_2022_2094506
crossref_primary_10_3390_app11104668
crossref_primary_10_1016_j_ijdrr_2024_104491
crossref_primary_10_1108_ECAM_07_2023_0655
crossref_primary_10_3390_su14010393
crossref_primary_10_1108_JEDT_02_2023_0040
Cites_doi 10.3390/economies5040046
10.1016/j.ijproman.2012.03.001
10.3846/1648715X.2016.1189975
10.1016/j.habitatint.2010.08.003
10.1108/IJDRBE-07-2019-0050
10.1108/17595901011056631
10.1108/ECAM-01-2013-0001
10.1108/DPM-01-2016-0006
10.1108/09653560610669882
10.1108/IJDRBE-03-2017-0018
10.1016/j.ijproman.2016.09.005
10.1108/17595901011026508
10.1016/j.iatssr.2012.07.001
10.1108/MRR-02-2013-0027
10.1177/0956247807082819
10.1108/IJMPB-10-2013-0054
10.1108/ECAM-10-2016-0232
10.1108/17595901111149141
10.1007/s13753-017-0155-4
10.1016/j.ijproman.2011.03.005
10.1108/ECAM-11-2017-0240
10.1108/IJDRBE-09-2018-0037
10.1177/1747493017711815
10.1108/17595901211263611
10.1016/j.habitatint.2013.10.005
10.1016/0007-6813(95)90054-3
10.1108/01443570210414310
10.1080/09613211003693945
10.1016/j.worlddev.2008.01.006
10.1002/pmj.21278
10.3126/jie.v14i1.20068
ContentType Journal Article
Copyright Emerald Publishing Limited
Emerald Publishing Limited 2020
Copyright_xml – notice: Emerald Publishing Limited
– notice: Emerald Publishing Limited 2020
DBID AAYXX
CITATION
0U~
1-H
7WY
7WZ
7XB
AFKRA
BENPR
BEZIV
CCPQU
DWQXO
F~G
K6~
K8~
L.-
L.0
M0C
PHGZM
PHGZT
PKEHL
PQBIZ
PQEST
PQQKQ
PQUKI
Q9U
DOI 10.1108/IJMPB-03-2020-0087
DatabaseName CrossRef
Global News & ABI/Inform Professional
Trade PRO
ProQuest ABI/INFORM Collection
ABI/INFORM Global (PDF only)
ProQuest Central (purchase pre-March 2016)
ProQuest Central UK/Ireland
ProQuest Central
Business Premium Collection
ProQuest One Community College
ProQuest Central Korea
ABI/INFORM Global (Corporate)
ProQuest Business Collection
DELNET Management Collection
ABI/INFORM Professional Advanced
ABI/INFORM Professional Standard
ABI/INFORM Global
ProQuest Central Premium
ProQuest One Academic
ProQuest One Academic Middle East (New)
ProQuest One Business
ProQuest One Academic Eastern Edition (DO NOT USE)
ProQuest One Academic
ProQuest One Academic UKI Edition
ProQuest Central Basic
DatabaseTitle CrossRef
Business Premium Collection
ABI/INFORM Global (Corporate)
ProQuest One Business
ABI/INFORM Global
ProQuest Central Basic
ProQuest One Academic Middle East (New)
ProQuest One Academic Eastern Edition
ProQuest One Community College
Trade PRO
ProQuest Business Collection
ABI/INFORM Complete
ProQuest Central
Global News & ABI/Inform Professional
ABI/INFORM Professional Advanced
ProQuest One Academic UKI Edition
ABI/INFORM Professional Standard
ProQuest Central Korea
ProQuest DELNET Management Collection
ProQuest One Academic
ProQuest Central (New)
ProQuest One Academic (New)
DatabaseTitleList
Business Premium Collection
Database_xml – sequence: 1
  dbid: BENPR
  name: ProQuest Central
  url: https://www.proquest.com/central
  sourceTypes: Aggregation Database
DeliveryMethod fulltext_linktorsrc
Discipline Business
EISSN 1753-8386
EndPage 787
ExternalDocumentID 10_1108_IJMPB_03_2020_0087
10.1108/IJMPB-03-2020-0087
GeographicLocations Angola
GeographicLocations_xml – name: Angola
GroupedDBID .WS
0R~
29J
3FY
4.4
5GY
5VS
70U
7WY
8R4
8R5
9F-
AADTA
AADXL
AAGMD
AAMCF
AAPBV
AAPSD
AAUDR
ABIJV
ABMQT
ABSDC
ACGFS
ACMTK
ADOMW
AEBZA
AEUCW
AFKRA
AFNZV
AHSMT
AJEBP
ALMA_UNASSIGNED_HOLDINGS
ASMFL
ATGMP
AUCOK
AVELQ
BENPR
BEZIV
BLEHN
BPHCQ
CS3
DWQXO
EBS
FNNZZ
GEI
GMX
GQ.
H13
HZ~
IPNFZ
J1Y
JL0
K6~
K8~
M0C
M42
MS~
O9-
P2P
PQBIZ
PQEST
PQQKQ
PQUKI
PROAC
Q2X
RIG
TDY
TGG
TMF
V1G
VP9
Z11
Z12
ZYZAG
AAGBP
AAKOT
AARQV
AAXBI
AAYXX
ABJNI
ABYQI
ACPVR
ACTSA
ADQHX
ADWNT
AFNTC
AGTVX
AHMHQ
AILOG
AODMV
CCPQU
CITATION
PHGZM
PHGZT
0U~
1-H
7XB
L.-
L.0
PKEHL
Q9U
ID FETCH-LOGICAL-c317t-a15361e588068577fb72a7eeed0c8ee70ec0b2c497133e5ec98d4f7e1cc3bc963
IEDL.DBID BENPR
ISSN 1753-8378
IngestDate Mon Jun 30 14:35:39 EDT 2025
Wed Jul 30 23:57:42 EDT 2025
Thu Apr 24 23:09:47 EDT 2025
Thu Feb 16 12:19:44 EST 2023
IsPeerReviewed true
IsScholarly true
Issue 3
Keywords Angola
Post-disaster reconstruction (PDR)
Challenges
Project management
Public sector
Language English
License Licensed re-use rights only
https://www.emerald.com/insight/site-policies
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c317t-a15361e588068577fb72a7eeed0c8ee70ec0b2c497133e5ec98d4f7e1cc3bc963
Notes ObjectType-Article-1
SourceType-Scholarly Journals-1
ObjectType-Feature-2
content type line 14
ORCID 0000-0002-1794-7255
PQID 2534137775
PQPubID 38494
PageCount 21
ParticipantIDs crossref_citationtrail_10_1108_IJMPB_03_2020_0087
emerald_primary_10_1108_IJMPB-03-2020-0087
crossref_primary_10_1108_IJMPB_03_2020_0087
proquest_journals_2534137775
PublicationCentury 2000
PublicationDate 2021-04-06
PublicationDateYYYYMMDD 2021-04-06
PublicationDate_xml – month: 04
  year: 2021
  text: 2021-04-06
  day: 06
PublicationDecade 2020
PublicationPlace Bingley
PublicationPlace_xml – name: Bingley
PublicationTitle International journal of managing projects in business
PublicationYear 2021
Publisher Emerald Publishing Limited
Emerald Group Publishing Limited
Publisher_xml – name: Emerald Publishing Limited
– name: Emerald Group Publishing Limited
References (key2022092113194371300_ref005) 2018; 7
(key2022092113194371300_ref014) 2007; 22
(key2022092113194371300_ref025) 2012; 3
UNDP (key2022092113194371300_ref056) 2009
(key2022092113194371300_ref046) 2020; ahead-of-print
(key2022092113194371300_ref020) 2010
(key2022092113194371300_ref011) 2014; 21
(key2022092113194371300_ref051) 2012; 43
(key2022092113194371300_ref037) 2014
(key2022092113194371300_ref057) 2012
(key2022092113194371300_ref503) 2017; 35
(key2022092113194371300_ref053) 2012
(key2022092113194371300_ref035) 2012; 36
(key2022092113194371300_ref504) 2017; 12
PMI (key2022092113194371300_ref043) 2013
(key2022092113194371300_ref502) 2017
(key2022092113194371300_ref009) 2010; 38
(key2022092113194371300_ref010) 2011; 35
(key2022092113194371300_ref054) 2016
(key2022092113194371300_ref036) 2006; 15
(key2022092113194371300_fur2) 2013
(key2022092113194371300_ref030) 2006
(key2022092113194371300_ref021) 2012; 30
(key2022092113194371300_ref018) 2019; 10
(key2022092113194371300_fur9) 2007
(key2022092113194371300_ref015) 2002; 22
(key2022092113194371300_fur8) 2010
(key2022092113194371300_ref027) 2008; 16
UNDP (key2022092113194371300_fur10) 2007
(key2022092113194371300_ref024) 2010
(key2022092113194371300_ref008) 2007; 19
(key2022092113194371300_ref003) 2011
(key2022092113194371300_fur5) 2011
(key2022092113194371300_ref007) 2006
(key2022092113194371300_ref023) 2013
(key2022092113194371300_fur11) 2014
(key2022092113194371300_ref017) 2018; 25
(key2022092113194371300_ref013) 2017; 8
(key2022092113194371300_fur1) 2012
(key2022092113194371300_ref016) 2007; 32
(key2022092113194371300_ref028) 2013; 31
(key2022092113194371300_ref059) 2002
(key2022092113194371300_ref501) 2017
World Bank (key2022092113194371300_ref058) 2013
(key2022092113194371300_ref060) 2014; 42
(key2022092113194371300_ref031) 2016; 25
ADB (key2022092113194371300_ref001) 2011
(key2022092113194371300_ref041) 2005
(key2022092113194371300_ref006) 2019; 10
(key2022092113194371300_ref012) 2012
(key2022092113194371300_ref019) 2010; 1
(key2022092113194371300_ref022) 2014
(key2022092113194371300_ref042) 2007; IX
(key2022092113194371300_ref047) 2019; 11
(key2022092113194371300_ref004) 2016; 20
(key2022092113194371300_ref039) 2013
(key2022092113194371300_ref045) 2009
(key2022092113194371300_ref038) 2007
(key2022092113194371300_ref040) 1978
(key2022092113194371300_ref061) 2009; 2
(key2022092113194371300_ref044) 2004; 22
key2022092113194371300_fur4
key2022092113194371300_fur6
(key2022092113194371300_ref050) 2008
(key2022092113194371300_ref002) 2011; 2
(key2022092113194371300_ref049) 2017; 17
(key2022092113194371300_ref052) 1999; 6
(key2022092113194371300_ref032) 2009; 37
(key2022092113194371300_fur3) 2018
(key2022092113194371300_ref048) 2014; 37
(key2022092113194371300_ref033) 2014; 7
(key2022092113194371300_ref055) 2018; 14
(key2022092113194371300_ref034) 2019; 26
(key2022092113194371300_ref029) 2009
(key2022092113194371300_ref026) 2010; 1
(key2022092113194371300_fur7) 1995; 38
References_xml – start-page: 889
  year: 2017
  ident: key2022092113194371300_ref502
  article-title: Inter-organizational disaster management projects: finding the middle way between trust and control
– start-page: 46
  year: 2017
  ident: key2022092113194371300_ref501
  article-title: Analysis of variance of the effects of a project’s location on key issues and challenges in post-disaster reconstruction projects
  doi: 10.3390/economies5040046
– volume: 17
  start-page: 238
  issue: 8
  year: 2017
  ident: key2022092113194371300_ref049
  article-title: Research on management model of post-disaster reconstruction based on contingency Theory-taking the post-disaster reconstruction project in Lushan as an example
  publication-title: Journal of Scientific and Engineering Research
– volume: 31
  start-page: 147
  issue: 1
  year: 2013
  ident: key2022092113194371300_ref028
  article-title: Breaking the vicious cycle of flood disasters: goals of project management in post-disaster rebuild projects
  publication-title: International Journal of Project Management
  doi: 10.1016/j.ijproman.2012.03.001
– volume: 20
  start-page: 265
  year: 2016
  ident: key2022092113194371300_ref004
  article-title: An analysis of issues for the management of post-disaster housing reconstruction
  publication-title: International Journal of Strategic Property Management
  doi: 10.3846/1648715X.2016.1189975
– ident: key2022092113194371300_fur4
– volume: 35
  start-page: 199
  year: 2011
  ident: key2022092113194371300_ref010
  article-title: Donor-driven resource procurement for post-disaster reconstruction: constraints and actions
  publication-title: Habitat International
  doi: 10.1016/j.habitatint.2010.08.003
– start-page: 1
  year: 2013
  ident: key2022092113194371300_ref039
  article-title: Effective time management in post-disaster reconstruction
– volume: ahead-of-print
  issue: ahead-of-print
  year: 2020
  ident: key2022092113194371300_ref046
  article-title: Barriers and enablers of coastal disaster resilience – lessons learned from tsunami in Sri Lanka
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/IJDRBE-07-2019-0050
– volume: 1
  start-page: 173
  year: 2010
  ident: key2022092113194371300_ref026
  article-title: Post-disaster housing reconstruction: comparative study of donor vs owner-driven approaches
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/17595901011056631
– volume: 21
  start-page: 291
  issue: 3
  year: 2014
  ident: key2022092113194371300_ref011
  article-title: Critical success factors for implementation of risk assessment and management practices within the Tanzanian construction industry
  publication-title: Engineering, Construction and Architectural Management
  doi: 10.1108/ECAM-01-2013-0001
– volume: 7
  start-page: 29
  issue: 2
  year: 2018
  ident: key2022092113194371300_ref005
  article-title: Practice framework for the management of post disaster housing reconstruction programmes
  publication-title: Sustainability Journal
– volume: 32
  start-page: 37
  issue: 5
  year: 2007
  ident: key2022092113194371300_ref016
  article-title: Allocation of post-disaster reconstruction financing to housing
  publication-title: Building Research and Information
– volume-title: Building Resilience: Integrating Climate and Disaster Risk into Development
  year: 2013
  ident: key2022092113194371300_ref058
– volume: 25
  start-page: 685
  issue: 5
  year: 2016
  ident: key2022092113194371300_ref031
  article-title: Critical success factors for post-disaster infrastructure recovery: learning from the Canterbury (NZ) earthquake recovery
  publication-title: Disaster Prevention and Management
  doi: 10.1108/DPM-01-2016-0006
– volume: 15
  start-page: 396
  issue: 3
  year: 2006
  ident: key2022092113194371300_ref036
  article-title: An integrated approach to natural disaster management: public project management and its critical success factors
  publication-title: Disaster Prevention and Management
  doi: 10.1108/09653560610669882
– volume: 10
  start-page: 151
  issue: 2/3
  year: 2019
  ident: key2022092113194371300_ref018
  article-title: A framework for reconstruction of road infrastructure after a disaster
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/IJDRBE-03-2017-0018
– volume: 35
  start-page: 913
  issue: 5
  year: 2017
  ident: key2022092113194371300_ref503
  article-title: The role of community leadership in disaster recovery projects: Tsunami lessons from Japan
  publication-title: International Journal of Project Management
  doi: 10.1016/j.ijproman.2016.09.005
– volume-title: The Study on Paradigm Shift of Project Management Based on Complexity Science – project Management Innovations in Shanghai 2010 EXPO Construction Program
  year: 2009
  ident: key2022092113194371300_ref045
– volume-title: Cheetah Project Management
  year: 2006
  ident: key2022092113194371300_ref030
– volume-title: From Vision to Implementation: Enhancing the Recovery Process through Integrated Knowledge, Planning, and Project Management
  year: 2011
  ident: key2022092113194371300_fur5
– volume: 22
  start-page: 26
  issue: 1
  year: 2007
  ident: key2022092113194371300_ref014
  article-title: Lessons learned from the housing re-construction following the Bam earthquake in Iran
  publication-title: The Australian Journal of Emergency Management
– volume: 1
  start-page: 103
  issue: 1
  year: 2010
  ident: key2022092113194371300_ref019
  article-title: An examination of decision making in post disaster housing reconstruction
  publication-title: Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/17595901011026508
– volume: 36
  start-page: 11
  issue: 1
  year: 2012
  ident: key2022092113194371300_ref035
  article-title: Reconstruction of the Aceh Region following the 2004 Indian Ocean tsunami disaster: a transportation perspective
  publication-title: IATSS Research
  doi: 10.1016/j.iatssr.2012.07.001
– volume: 37
  start-page: 308
  issue: 3
  year: 2014
  ident: key2022092113194371300_ref048
  article-title: Designing and using research questionnaires
  publication-title: Management Research Review
  doi: 10.1108/MRR-02-2013-0027
– volume: 11
  issue: 3
  year: 2019
  ident: key2022092113194371300_ref047
  article-title: Identification and categorization of policy and legal barriers to long-term timely post disaster reconstruction
  publication-title: Journal of Legal Affairs and Dispute Resolution in Engineering and Construction
– volume-title: Social Research Methods
  year: 2012
  ident: key2022092113194371300_fur1
– volume: 19
  start-page: 361
  year: 2007
  ident: key2022092113194371300_ref008
  article-title: Housing microfinance in post-conflict Angola, Overcoming socioeconomic exclusion through land tenure and access to credit
  publication-title: Environment and Urbanization
  doi: 10.1177/0956247807082819
– volume: 7
  start-page: 327
  issue: 3
  year: 2014
  ident: key2022092113194371300_ref033
  article-title: Re-conceptualising ‘Building Back Better’ to improve post disaster recovery
  publication-title: International Journal of Managing Projects in Business
  doi: 10.1108/IJMPB-10-2013-0054
– volume: 25
  start-page: 113
  issue: 1
  year: 2018
  ident: key2022092113194371300_ref017
  article-title: Fcators affecting the accuracy of cost estimate: case of Jordan
  publication-title: Engineering, Construction and Architecural Management
  doi: 10.1108/ECAM-10-2016-0232
– start-page: 28
  year: 2007
  ident: key2022092113194371300_fur9
  article-title: Critical success factors in project management globally and how they may be applied to aid projects
– volume: 2
  start-page: 148
  issue: 2
  year: 2011
  ident: key2022092113194371300_ref002
  article-title: An overview of post-disaster permanent housing reconstruction in developing countries
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/17595901111149141
– volume: 8
  start-page: 402
  year: 2017
  ident: key2022092113194371300_ref013
  article-title: Factors influencing post-disaster reconstruction project management for housing provision in the Gaza Strip, Occupied Palestinian Territories
  publication-title: International Journal of Disaster Risk Science
  doi: 10.1007/s13753-017-0155-4
– volume: 30
  start-page: 105
  issue: 1
  year: 2012
  ident: key2022092113194371300_ref021
  article-title: Critical success factors for World Bank projects: an empirical investigation
  publication-title: International Journal of Project Management
  doi: 10.1016/j.ijproman.2011.03.005
– volume: 26
  start-page: 1962
  issue: 9
  year: 2019
  ident: key2022092113194371300_ref034
  article-title: Infrastructure procurement capacity gaps in Nigeria public sector institutions
  publication-title: Engineering, Construction and Architectural Management
  doi: 10.1108/ECAM-11-2017-0240
– volume: 10
  start-page: 14
  issue: 1
  year: 2019
  ident: key2022092113194371300_ref006
  article-title: Exploring Indian post-disaster temporary housing strategy through a comparative review
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/IJDRBE-09-2018-0037
– volume-title: Survey: Housing Projects Delayed for more than 10,000 Evacuees
  year: 2013
  ident: key2022092113194371300_ref023
– volume: 12
  start-page: 472
  issue: 5
  year: 2017
  ident: key2022092113194371300_ref504
  article-title: Improving the development, monitoring and reporting of stroke rehabilitation research: consensus-based core recommendations from the stroke recovery and rehabilitation roundtable
  publication-title: International Journal of Stroke
  doi: 10.1177/1747493017711815
– volume: 2
  start-page: 386
  year: 2009
  ident: key2022092113194371300_ref061
  article-title: A project management prospective in achieving a sustainable supply chain for timber procurement in Banda Aceh, Indonesia
  publication-title: International Journal of Managing Projects in Business
– volume: 3
  start-page: 220
  issue: 3
  year: 2012
  ident: key2022092113194371300_ref025
  article-title: The sense of place in the new homes of post-Bam earthquake reconstruction
  publication-title: International Journal of Disaster Resilience in the Built Environment
  doi: 10.1108/17595901211263611
– start-page: 292
  year: 2012
  ident: key2022092113194371300_ref053
  article-title: Rebuilding housing after a disaster: factors for failure
– volume-title: Aceh-Nias Reconstruction and Rehabilitation: Progress and Challenges at the End of 2006
  year: 2007
  ident: key2022092113194371300_ref038
– start-page: 1269
  year: 2010
  ident: key2022092113194371300_ref020
  article-title: A literature review of the role of project management in post-disaster reconstruction
– volume-title: A Guide to the Project Management Body of Knowledge (PMBOK)
  year: 2013
  ident: key2022092113194371300_ref043
– volume-title: Angola 2011-2015 Country Strategy Paper and 2010 Country Portfolio Performance Review
  year: 2011
  ident: key2022092113194371300_ref001
– start-page: 4
  volume-title: Haitians Still Homeless, “Suffering in Despair” 4 yrs after Quake – Amnesty
  year: 2014
  ident: key2022092113194371300_ref037
– year: 2008
  ident: key2022092113194371300_ref050
  article-title: Houses or homes? The patterns of design
– volume-title: Research Design: Qualitative, Quantitative, and Mixed Methods Approaches
  year: 2018
  ident: key2022092113194371300_fur3
– volume-title: Research Methods for Business Students
  year: 2016
  ident: key2022092113194371300_ref054
– volume: 42
  start-page: 21
  year: 2014
  ident: key2022092113194371300_ref060
  article-title: Research trends of post disaster reconstruction: the past and the future
  publication-title: Habitat International
  doi: 10.1016/j.habitatint.2013.10.005
– volume: 38
  start-page: 41
  issue: 2
  year: 1995
  ident: key2022092113194371300_fur7
  article-title: Lessons for an accidental profession
  publication-title: Bus Horizons
  doi: 10.1016/0007-6813(95)90054-3
– ident: key2022092113194371300_fur6
– volume: 22
  start-page: 152
  issue: 2
  year: 2002
  ident: key2022092113194371300_ref015
  article-title: Survey research in operations management: a process-based perspective
  publication-title: International Journal of Operations and Production Management
  doi: 10.1108/01443570210414310
– start-page: 120
  year: 2014
  ident: key2022092113194371300_ref022
  article-title: Project management success for post-disaster reconstruction projects: international NGOs perspectives
– volume: 38
  start-page: 247
  issue: 3
  year: 2010
  ident: key2022092113194371300_ref009
  article-title: Resourcing challenges for post-disaster housing reconstruction: a comparative analysis
  publication-title: Building Research and Information
  doi: 10.1080/09613211003693945
– volume-title: SPSS Survival Manual: A Step by Step Guide to Data Analysis Using Version 12
  year: 2005
  ident: key2022092113194371300_ref041
– start-page: 1
  year: 2002
  ident: key2022092113194371300_ref059
  article-title: Integrated relief and reconstruction management following A natural disaster. Second annual IIASA-DPRI meeting
– start-page: 123
  year: 2012
  ident: key2022092113194371300_ref012
  article-title: Building capability for disaster resilience
– volume: 37
  start-page: 385
  issue: 2
  year: 2009
  ident: key2022092113194371300_ref032
  article-title: Building back better: the large-scale impact of small-scale Approaches to reconstruction
  publication-title: World Development
  doi: 10.1016/j.worlddev.2008.01.006
– volume-title: Psychometric Theory
  year: 1978
  ident: key2022092113194371300_ref040
– volume-title: Participatory Reconstruction Process at Work: Re-building Homes in Aceh and Nias, UN-habitat and UNDP Joint Programme in Aceh
  year: 2007
  ident: key2022092113194371300_fur10
– volume: 43
  start-page: 5
  issue: 4
  year: 2012
  ident: key2022092113194371300_ref051
  article-title: Project management trilogy challenges in Africa –where to from here?
  publication-title: Project Management Journal
  doi: 10.1002/pmj.21278
– start-page: 292
  year: 2012
  ident: key2022092113194371300_ref057
  article-title: Rebuilding housing after a disaster: factors for failure
– volume-title: Lessons from Aceh: Key Considerations in Post-disaster Reconstruction
  year: 2010
  ident: key2022092113194371300_fur8
– start-page: 17
  year: 2011
  ident: key2022092113194371300_ref003
  article-title: A project management approach to disaster response and recovery operations
– volume: IX
  start-page: 1
  issue: IX
  year: 2007
  ident: key2022092113194371300_ref042
  article-title: Project management for emergency response and disaster recovery – a call to arms!
  publication-title: PM World Today Journal
– volume: 16
  start-page: 25
  issue: 1
  year: 2008
  ident: key2022092113194371300_ref027
  article-title: The meaning of ‘build back better’: evidence from post-tsunami Aceh and Sri Lanka
  publication-title: Journal of Contingencies and Crisis Management
– volume-title: Knowledge Transfer in Post-Disaster Reconstruction: The Problem of Post-Post-Disaster Reconstruction
  year: 2009
  ident: key2022092113194371300_ref029
– volume-title: Safer Homes, Stronger Communities: A Handbook for Reconstructing after Natural Disasters
  year: 2010
  ident: key2022092113194371300_ref024
– volume: 6
  start-page: 335
  issue: 4
  year: 1999
  ident: key2022092113194371300_ref052
  article-title: Tracing the african project failure syndrome: the significance of ‘ubuntu’
  publication-title: Engineering Construction and Architectural Management Journal
– volume: 14
  start-page: 52
  issue: 1
  year: 2018
  ident: key2022092113194371300_ref055
  article-title: Post-disaster reconstruction after 2015 gorkha earthquake: challenges and influencing factors
  publication-title: Journal of the Institute of Engineering
  doi: 10.3126/jie.v14i1.20068
– volume-title: Capacity Development: A UNDP Primer
  year: 2009
  ident: key2022092113194371300_ref056
– volume: 22
  start-page: 787e797
  year: 2004
  ident: key2022092113194371300_ref044
  article-title: Analysing construction project coalition: exploring the application of social network analysis
  publication-title: Construction Management and Economics
– volume-title: Qualitative Inquiry and Research Design: Choosing Among Five Approaches
  year: 2013
  ident: key2022092113194371300_fur2
– volume-title: Case Study Research Design and Methods
  year: 2014
  ident: key2022092113194371300_fur11
– year: 2006
  ident: key2022092113194371300_ref007
  article-title: Building A safer Aceh, reconstruction of houses, one year after the December 26, 2004 Tsunami
SSID ssj0069411
Score 2.2814784
Snippet PurposeDespite the extensive research on post-disaster reconstruction projects (PDRP), there is a paucity of studies that examine critical challenges for the...
SourceID proquest
crossref
emerald
SourceType Aggregation Database
Enrichment Source
Index Database
Publisher
StartPage 767
SubjectTerms Civil war
Disasters
Failure
Flexibility
International organizations
Operations management
Project management
Public sector
Strategic planning
Success
War
SummonAdditionalLinks – databaseName: Emerald Management eJournals
  dbid: ZYZAG
  link: http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwrV1LS8QwEB58gHjxLa4vcvCkxE3TpMl6W8UnKHtQUC-lTVNd1LrSevHXm0nbFUU8eW5aSDJ88-g33wDshCYItcgDaozOqMiYpNryiMpUMCucAxa-SezyKjq7ERe38nYCBm0vjKdV1uUYj9PDosQktYvEbYfCY8EBnF5zfnE5OEQ-EMccCMXVuliz7j5WL8-TMM2DiDk7n76_u--ftuiMfZs-CXNhOkUx9baR5tfvfXNWPzp2v1Dbu6KTeXhrN1EzUJ7236t033z80Hf8z10uwFwTt5J-bWiLMGGLJZhpafPLUAzqkg55GfNpiGkHtZTEhcZk9FpWNBuWCWozEJ-Jj9VrSVMRKsmwIP3iwSXcByQhtQg3Kf2vBTL6agxdgZuT4-ujM9rMcqDGRSgVTRyyRoGVDi4iLZXKU8UTZZ2HZkZbq5g1LOVG9DBpttKans5ErmxgTJgahxKrMFW8FnYNiFZZmjMtemEeiiTjCUtyrVwYKXNudaI7ELSXFptG6BznbTzHPuFhOvZHGrMwxiON8Ug7sDd-Z1TLfPy5ere5vd8Xf7utDmy25hI3-FDGXGL0oJSS638_3oBZjiwa5ApFmzDlrsVuuTCoSrcby_4EA5QBrA
  priority: 102
  providerName: Emerald
Title Project management challenges for post-disaster reconstruction projects in Angola: a public sector perspective
URI https://www.emerald.com/insight/content/doi/10.1108/IJMPB-03-2020-0087/full/html
https://www.proquest.com/docview/2534137775
Volume 14
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwfV3NS8MwFA-6gXgRP3E6JQdPSliaJk3mRTbZnIONIQ7mLiVNUxloV-n-f0zadGMiO_XQ9PJe3u999L3fA-DOV54vaOIhpUSMaIwZEpoEiEUUa2ocMC2GxEbjYDClwxmbuYJb7toqK0wsgDpeKlsjbxFm8ZZzzp6yH2S3Rtm_q26Fxj6oGwgWogbq3d548lZhsZ3SLFIuE5QjS51ejc1g0XodjiZd201EbAZlqdm2XNOf-dwNRheOp38MjlzECDulik_Ank5PwUHVsH4G0klZTIHf604WqKoVKTk0QSnMlvkKxYtcWlYEWOTAa95Y6GoxOVyksJN-mlT3EUpY0l_DvCjqw2wzknkOpv3e-_MAuS0KSJnYYIWkwbTA08wYaiAY50nEieTa-EashNYca4UjomjbpquaadUWMU249pTyI2Xs8wLU0mWqLwEUPI4SLGjbT3wqYyKxTAQ3ARxLiBZSNIBXCTBUjmLcbrr4CotUA4uwEHqI_dAKPbRCb4CH9TdZSbCx8_S908v_h7f02QDNSnWhs8w83Nyjq92vr8Ehsf0rtksnaIKaUYu-MQHIKrp1t8w85x_zzssvGIXY6g
linkProvider ProQuest
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwtV3fT9swED5BkQYvaD-YVmCbH8YLyMJx7NidNE2wgVqgVYVA4s1LHGdCgrQolRD_FH_jfEncCjTxxnOcPNxd7u47330H8C22UaxFEVFrdU5FziTVjidUZoI54QOwqIfEhqOkfylOruTVEjyGWRhsqww-sXbU-cRijXyfS_S3Sin5c3pHcWsU3q6GFRqNWZy6h3sP2aofg99evzucHx9d_OrTdqsAtT5Wzmjq__EkctIbbqKlUkWmeKqcjxXMaucUc5Zl3Ioewjcnne3pXBTKRdbGmfX26r-7DCsiThjvwMrh0Wh8Hnw_ToXWEM-DAIpU7WFMh-n9wclwfIjdSxwRG1LBPQmFz-aBFzGhDnTHb2G9zVDJQWNS72DJle_hTWiQ_wDluCnekNt55wyxYSVLRXwSTKaTakbz6ypFFgZSY-45Ty1paz8VuS7JQfnXQ-vvJCUN3Tap6ksEMl2MgG7A5avI9yN0yknpPgHRKs8KpkUvLmKR5jxlaaGVTxhlwZ1OdReiIEBjW0pz3KxxY2pow7SphW5YbFDoBoXehb35O9OG0OPF07utXv5_-Ik-u7AdVGdaT1CZhd1uvvz4K6z2L4Zn5mwwOt2CNY69M9ghlGxDx6vIffbJzyz70locgT-vbeT_ADBjFMo
linkToPdf http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwtV3dT9swED-xVkJ7mWADreNjftheNll1HDt2JyFEgYrCqCoEEm9e4jgIaUuLUgntX9tfN18St2KaeOM5Th7ufrm73_k-AD7FNoq1KCJqrc6pyJmk2vGEykwwJ7wDFnWT2OUkObsR57fydg3-hF4YLKsMNrE21PnMYo68zyXaW6WU7BdtWcT0ZHQ4f6C4QQpvWsM6jQYiF-73o6dv1cH4xOv6M-ej0-vjM9puGKDW-80FTf3_nkROehAnWipVZIqnynm_wax2TjFnWcatGCCVc9LZgc5FoVxkbZxZj13_3VfQVciKOtAdnk6mV8EPYIdoTfc8IaA4tj207DDdH59fTodYycSRveFYuCdu8Z_e4JV_qJ3eaAPetNEqOWrgtQlrrnwL66FY_h2U0yaRQ34tq2iIDetZKuIDYjKfVQua31cpTmQgNf9ezqwlbR6oIvclOSrvPM3-RlLSjN4mVX2hQOardtAtuHkR-W5Dp5yV7j0QrfKsYFoM4iIWac5TlhZa-eBRFtzpVPcgCgI0th1vjls2fpqa5jBtaqEbFhsUukGh9-Dr8p15M9zj2dNfWr38__ATffZgN6jOtFahMisMf3j-8UdY9-A238eTix14zbGMBouFkl3oeA25PR8HLbL9FnAEfrw0xv8C_CUY_w
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Project+management+challenges+for+post-disaster+reconstruction+projects+in+Angola%3A+a+public+sector+perspective&rft.jtitle=International+journal+of+managing+projects+in+business&rft.au=Nyamagere+Gladys+Sospeter&rft.au=Pantaleo+MD+Rwelamila&rft.au=Gimbi%2C+Joaqium&rft.date=2021-04-06&rft.pub=Emerald+Group+Publishing+Limited&rft.issn=1753-8378&rft.eissn=1753-8386&rft.volume=14&rft.issue=3&rft.spage=767&rft.epage=787&rft_id=info:doi/10.1108%2FIJMPB-03-2020-0087&rft.externalDBID=HAS_PDF_LINK
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=1753-8378&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=1753-8378&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=1753-8378&client=summon