Examining Factors Affecting Budget Overrun of Construction Projects Undertaken through Management Procurement Method Using PLS-sem Approach

This paper focused on examining the effect of various factors on budget overrun in construction projects undertaken using management procurement method in Malaysia. It adopted a quantitative method for data collection using structured questionnaire survey amongst contractors, consultant and clients....

Full description

Saved in:
Bibliographic Details
Published inProcedia, social and behavioral sciences Vol. 107; pp. 120 - 128
Main Authors Rahman, Ismail Abdul, Memon, Aftab Hameed, Karim, Ahmad Tarmizi Abd
Format Journal Article
LanguageEnglish
Published Elsevier Ltd 11.12.2013
Subjects
Online AccessGet full text

Cover

Loading…
Abstract This paper focused on examining the effect of various factors on budget overrun in construction projects undertaken using management procurement method in Malaysia. It adopted a quantitative method for data collection using structured questionnaire survey amongst contractors, consultant and clients. A total of 118 samples were collected against 200 questionnaires that had been distributed nationwide. Gathered data was analyzed with an advanced multivariate method of structural equation modeling with PLS approach using SmartPLS software. The major finding showed all the constructs in model contributed significantly to budget overrun with R2 value of 0.623. Also, the developed model has substantial explaining power with GoF value of 0.62. This indicates that the model was able to be generalized in representing the budget overrun factors occurring in construction projects nationwide. By identifying these factors, it will help the construction community to take measures in improving the cost performance of the projects.
AbstractList This paper focused on examining the effect of various factors on budget overrun in construction projects undertaken using management procurement method in Malaysia. It adopted a quantitative method for data collection using structured questionnaire survey amongst contractors, consultant and clients. A total of 118 samples were collected against 200 questionnaires that had been distributed nationwide. Gathered data was analyzed with an advanced multivariate method of structural equation modeling with PLS approach using SmartPLS software. The major finding showed all the constructs in model contributed significantly to budget overrun with R2 value of 0.623. Also, the developed model has substantial explaining power with GoF value of 0.62. This indicates that the model was able to be generalized in representing the budget overrun factors occurring in construction projects nationwide. By identifying these factors, it will help the construction community to take measures in improving the cost performance of the projects.
Author Memon, Aftab Hameed
Karim, Ahmad Tarmizi Abd
Rahman, Ismail Abdul
Author_xml – sequence: 1
  givenname: Ismail Abdul
  surname: Rahman
  fullname: Rahman, Ismail Abdul
– sequence: 2
  givenname: Aftab Hameed
  surname: Memon
  fullname: Memon, Aftab Hameed
  email: aftabm78@hotmail.com
– sequence: 3
  givenname: Ahmad Tarmizi Abd
  surname: Karim
  fullname: Karim, Ahmad Tarmizi Abd
BookMark eNp9kEtOwzAQhi1UJErpDVj4Agl-pEmzQSpVC0hFrQRdW449SVOIXdlJBWfg0jgKC1bMZkbz-PXPd41GxhpA6JaSmBKa3h1jX_iTszEjlMeUxQnJLtCYzrMsIgmbj_7UV2jq_ZGE4JTnjI3R9-pTNrWpTYXXUrXWebwoS1Bt33nodAUt3p7Buc5gW-KlNb51XRhbg3fOHsOmx3ujwbXyHQxuD8521QG_SCMraMC0_Zrq3FC_QHuwGu99L7_bvEYeGrw4BftSHW7QZSk_PEx_8wTt16u35VO02T4-LxebSNE8PJKSHBTVnEKugWcZKJIAyWec6ZznMJuHd2meFClJMqkzzhJZUJWWjOlkVtKCT1Ay6CpnvXdQipOrG-m-BCWiZyqOYmAqeqaCMhGYhrP74QyCt3MNTnhVg1GgaxcwCG3r_wV-ABcVhgQ
CitedBy_id crossref_primary_10_1057_s41284_021_00326_x
crossref_primary_10_1016_j_procs_2021_01_275
crossref_primary_10_1080_15389588_2024_2341384
crossref_primary_10_1007_s11119_024_10156_7
crossref_primary_10_1108_IJPL_06_2017_0025
crossref_primary_10_1108_EMJB_12_2022_0211
crossref_primary_10_1007_s40808_022_01526_z
crossref_primary_10_1080_15389588_2023_2236261
crossref_primary_10_1080_17457300_2023_2214885
crossref_primary_10_1108_ECAM_03_2019_0123
crossref_primary_10_3934_era_2023048
crossref_primary_10_54452_jrb_1363303
crossref_primary_10_1080_15623599_2020_1840010
crossref_primary_10_1177_03611981241230305
crossref_primary_10_1016_j_sintl_2022_100194
crossref_primary_10_5861_ijrsm_2018_2002
crossref_primary_10_1080_17452007_2023_2282121
crossref_primary_10_1016_j_jth_2022_101462
crossref_primary_10_1016_j_jth_2022_101560
crossref_primary_10_3389_fpsyg_2022_878514
crossref_primary_10_3390_su15021114
crossref_primary_10_3390_su14020596
crossref_primary_10_1108_F_04_2015_0015
crossref_primary_10_1016_j_jth_2023_101741
crossref_primary_10_1080_23311916_2017_1383638
Cites_doi 10.4135/9781483348957
10.1002/asi.21442
10.1007/978-3-540-32827-8_29
10.1007/978-1-4419-1280-0_2
10.1080/01446193.2011.564195
10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7
10.1007/978-3-540-32827-8_3
10.1016/j.ijproman.2006.11.007
10.1177/002224378101800104
10.2307/20650284
10.2753/MTP1069-6679190202
10.1108/14635771011036357
ContentType Journal Article
Copyright 2013 The Authors
Copyright_xml – notice: 2013 The Authors
DBID 6I.
AAFTH
AAYXX
CITATION
DOI 10.1016/j.sbspro.2013.12.407
DatabaseName ScienceDirect Open Access Titles
Elsevier:ScienceDirect:Open Access
CrossRef
DatabaseTitle CrossRef
DatabaseTitleList
DeliveryMethod fulltext_linktorsrc
Discipline Social Sciences (General)
EISSN 1877-0428
EndPage 128
ExternalDocumentID 10_1016_j_sbspro_2013_12_407
S1877042813050301
GroupedDBID 0R~
0SF
4.4
457
5VS
6I.
71M
AACTN
AAEDT
AAEDW
AAFTH
AAIKJ
AALRI
AAQFI
AAXUO
ABMAC
ACGFS
ADBBV
ADEZE
AEXQZ
AGHFR
AITUG
ALMA_UNASSIGNED_HOLDINGS
AMRAJ
E3Z
EBS
EJD
EP2
EP3
F5P
FDB
FEDTE
FNPLU
HVGLF
IXB
KQ8
NCXOZ
O-L
O9-
OK1
OZT
ROL
SES
SSZ
XH2
AAYXX
ADVLN
CITATION
HZ~
ID FETCH-LOGICAL-c1977-609ec1d31e9de377ec04e09532d939e58187194b6047ad7324ab1c6f22d45f1b3
IEDL.DBID IXB
ISSN 1877-0428
IngestDate Fri Aug 23 03:33:00 EDT 2024
Fri Feb 23 02:30:15 EST 2024
IsDoiOpenAccess true
IsOpenAccess true
IsPeerReviewed true
IsScholarly true
Keywords Management Procurement Method
Budget overrun
PLS-SEM
Language English
License http://creativecommons.org/licenses/by-nc-nd/3.0
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c1977-609ec1d31e9de377ec04e09532d939e58187194b6047ad7324ab1c6f22d45f1b3
OpenAccessLink https://www.sciencedirect.com/science/article/pii/S1877042813050301
PageCount 9
ParticipantIDs crossref_primary_10_1016_j_sbspro_2013_12_407
elsevier_sciencedirect_doi_10_1016_j_sbspro_2013_12_407
PublicationCentury 2000
PublicationDate 2013-12-11
PublicationDateYYYYMMDD 2013-12-11
PublicationDate_xml – month: 12
  year: 2013
  text: 2013-12-11
  day: 11
PublicationDecade 2010
PublicationTitle Procedia, social and behavioral sciences
PublicationYear 2013
Publisher Elsevier Ltd
Publisher_xml – name: Elsevier Ltd
References Barclay, Thompson, Higgins (bib0025) 1995; 2
Ringle, C.M., Wende, S., & Will, S. 2005. SmartPLS 2.0 (M3) Beta, Hamburg 2005, http://www.smartpls.de.
Vinzi, V.E., Trinchera, L., & Amato, S. 2010. PLS Path Modeling: From Foundations to Recent Developments and Open Issues for Model Assessment and Improvement. In
Ringle, C.M., Sarstedt, M., & Mooi, E.A. 2010. Response-Based Segmentation Using Finite Mixture Partial Least Squares Theoretical Foundations and an Application to American Customer Satisfaction Index Data. In
Endut, I.R., Akintoye, A., & Kelly, J. 2009. Cost and time overruns of projects in Malaysia. retrieved on August 21, 2009, from http://www.irbnet.de/daten/iconda/CIB10633.pdf, 243-252.
(2), 139-151.
Abdullah, M.R., Aziz, A.A. A., & Rahman, I.A. 2009. Causes of delay and its effects in large MARA construction project.
Morledge, R., Smith, A., & Kashiwagi, D.T. 2006.
Aibinu, Ling, Ofori (bib0015) 2011; 29
(Third ed.): Lawrence Erlbaum Associates, Publishers, Mahwah, New Jersey, London.
(pp. 47-82).
Abdullah, M.R. 2010.
Akter, Ambra, Ray (bib0020) 2011; 62
Sage, Thousand Oaks, CA.
Hulland (bib0070) 1999; 20
Cohen, J. 1988. Statistical power analysis for the behavioral sciences (2nd ed.).
Chin, W.W. 1998. The partial least squares approach to structural equation modelling. In G. A. Marcoulides (Ed.)
Litwin, M.S. 1995.
Master thesis, University Tun Hussein Onn Malaysia.
(pp. 295-336): Erlbaum, Mahwah, NJ.
Blackwell Publishing, UK.
Cohen, J., Cohen, P., West, S.G., & Aiken, L.S. 2003.
Hair, J.F., Ringle, C.M., & Sarstedt, M. 2011. PLS-SEM: Indeed a Silver Bullet.
.
Sambasivan, Soon (bib0105) 2007; 25
Chin, W.W. 2010. How to Write Up and Report PLS Analyses. In V. Esposito Vinzi et al. (eds.) (Ed.)
Ibrahim, Roy, Ahmed, Imtiaz (bib0075) 2010; 17
(Vol. 8, pp. 19-49): R. Stahlbock et al. (eds.).
Fornell, Larcker (bib0055) 1981; 18
Springer- Verlag Berlin Heidelberg.
Rashid, R.A., Taib, I.M., Ahmad, W.B. W., Nasid, M.A., Ali, W.N. W., & Zainordin, Z.M. 2006. Effect of procurement systems on the performance of construction projects. Paper presented at the Padang on 21-24 June 2006, Retrieved from http://eprints.utm.my/790/dated: January 09, 2013.
Wetzels, Schroder, Oppen (bib0115) 2009; 33
Gefen, Straub, Boudreau (bib0060) 2000; 4
Fornell (10.1016/j.sbspro.2013.12.407_bib0055) 1981; 18
Hulland (10.1016/j.sbspro.2013.12.407_bib0070) 1999; 20
Akter (10.1016/j.sbspro.2013.12.407_bib0020) 2011; 62
Barclay (10.1016/j.sbspro.2013.12.407_bib0025) 1995; 2
Sambasivan (10.1016/j.sbspro.2013.12.407_bib0105) 2007; 25
Wetzels (10.1016/j.sbspro.2013.12.407_bib0115) 2009; 33
10.1016/j.sbspro.2013.12.407_bib0040
10.1016/j.sbspro.2013.12.407_bib0095
10.1016/j.sbspro.2013.12.407_bib0050
10.1016/j.sbspro.2013.12.407_bib0080
10.1016/j.sbspro.2013.12.407_bib0090
10.1016/j.sbspro.2013.12.407_bib0035
10.1016/j.sbspro.2013.12.407_bib0045
10.1016/j.sbspro.2013.12.407_bib0100
Ibrahim (10.1016/j.sbspro.2013.12.407_bib0075) 2010; 17
10.1016/j.sbspro.2013.12.407_bib0030
10.1016/j.sbspro.2013.12.407_bib0085
10.1016/j.sbspro.2013.12.407_bib0110
10.1016/j.sbspro.2013.12.407_bib0010
10.1016/j.sbspro.2013.12.407_bib0065
10.1016/j.sbspro.2013.12.407_bib0005
Aibinu (10.1016/j.sbspro.2013.12.407_bib0015) 2011; 29
Gefen (10.1016/j.sbspro.2013.12.407_bib0060) 2000; 4
References_xml – volume: 25
  start-page: 517
  year: 2007
  end-page: 526
  ident: bib0105
  article-title: Causes and effects of delays in Malaysian construction industry
  publication-title: International Journal of Project Management
  contributor:
    fullname: Soon
– volume: 62
  start-page: 100
  year: 2011
  end-page: 116
  ident: bib0020
  article-title: Trustworthiness in mHealth Information Services: An Assessment of a Hierarchical Model with Mediating and Moderating Effects Using Partial Least Squares (PLS)
  publication-title: Journal Of The American Society For Information Science And Technology
  contributor:
    fullname: Ray
– volume: 29
  start-page: 463
  year: 2011
  end-page: 481
  ident: bib0015
  article-title: Structural equation modeling of organizational justice and cooperative behaviour in the construction project claims process: contractors’ perspectives
  publication-title: Construction Management and Economics
  contributor:
    fullname: Ofori
– volume: 33
  start-page: 177
  year: 2009
  end-page: 195
  ident: bib0115
  article-title: Using PLS path modeling for assessing hierarchical construct models: Guidelines and empirical illustration
  publication-title: MIS Quarterly
  contributor:
    fullname: Oppen
– volume: 4
  start-page: 1
  year: 2000
  end-page: 78
  ident: bib0060
  article-title: Structural equation modelling and regression: Guidelines for research practice
  publication-title: Communications of the Association for Information Systems
  contributor:
    fullname: Boudreau
– volume: 20
  start-page: 195
  year: 1999
  end-page: 204
  ident: bib0070
  article-title: Use of partial least squares (PLS) in strategic management research: a review of four recent studies
  publication-title: Strategic Management Journal
  contributor:
    fullname: Hulland
– volume: 18
  start-page: 39
  year: 1981
  end-page: 50
  ident: bib0055
  article-title: Evaluating structural equation models with unobservable variables and measurement error
  publication-title: Journal of Marketing Research
  contributor:
    fullname: Larcker
– volume: 17
  start-page: 294
  year: 2010
  end-page: 308
  ident: bib0075
  article-title: An investigation of the status of the Malaysian construction industry
  publication-title: Benchmarking: An International Journal
  contributor:
    fullname: Imtiaz
– volume: 2
  start-page: 285
  year: 1995
  end-page: 309
  ident: bib0025
  article-title: The Partial Least Squares (PLS) approach to causal modeling: personal computer adoption and use as an illustration
  publication-title: Technology Studies
  contributor:
    fullname: Higgins
– ident: 10.1016/j.sbspro.2013.12.407_bib0080
  doi: 10.4135/9781483348957
– ident: 10.1016/j.sbspro.2013.12.407_bib0085
– volume: 62
  start-page: 100
  issue: 1
  year: 2011
  ident: 10.1016/j.sbspro.2013.12.407_bib0020
  article-title: Trustworthiness in mHealth Information Services: An Assessment of a Hierarchical Model with Mediating and Moderating Effects Using Partial Least Squares (PLS)
  publication-title: Journal Of The American Society For Information Science And Technology
  doi: 10.1002/asi.21442
  contributor:
    fullname: Akter
– ident: 10.1016/j.sbspro.2013.12.407_bib0010
– volume: 4
  start-page: 1
  issue: 5
  year: 2000
  ident: 10.1016/j.sbspro.2013.12.407_bib0060
  article-title: Structural equation modelling and regression: Guidelines for research practice
  publication-title: Communications of the Association for Information Systems
  contributor:
    fullname: Gefen
– ident: 10.1016/j.sbspro.2013.12.407_bib0035
  doi: 10.1007/978-3-540-32827-8_29
– ident: 10.1016/j.sbspro.2013.12.407_bib0100
– ident: 10.1016/j.sbspro.2013.12.407_bib0030
– volume: 2
  start-page: 285
  issue: 2
  year: 1995
  ident: 10.1016/j.sbspro.2013.12.407_bib0025
  article-title: The Partial Least Squares (PLS) approach to causal modeling: personal computer adoption and use as an illustration
  publication-title: Technology Studies
  contributor:
    fullname: Barclay
– ident: 10.1016/j.sbspro.2013.12.407_bib0090
– ident: 10.1016/j.sbspro.2013.12.407_bib0050
– ident: 10.1016/j.sbspro.2013.12.407_bib0095
  doi: 10.1007/978-1-4419-1280-0_2
– volume: 29
  start-page: 463
  issue: 5
  year: 2011
  ident: 10.1016/j.sbspro.2013.12.407_bib0015
  article-title: Structural equation modeling of organizational justice and cooperative behaviour in the construction project claims process: contractors’ perspectives
  publication-title: Construction Management and Economics
  doi: 10.1080/01446193.2011.564195
  contributor:
    fullname: Aibinu
– volume: 20
  start-page: 195
  year: 1999
  ident: 10.1016/j.sbspro.2013.12.407_bib0070
  article-title: Use of partial least squares (PLS) in strategic management research: a review of four recent studies
  publication-title: Strategic Management Journal
  doi: 10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7
  contributor:
    fullname: Hulland
– ident: 10.1016/j.sbspro.2013.12.407_bib0110
  doi: 10.1007/978-3-540-32827-8_3
– ident: 10.1016/j.sbspro.2013.12.407_bib0005
– volume: 25
  start-page: 517
  year: 2007
  ident: 10.1016/j.sbspro.2013.12.407_bib0105
  article-title: Causes and effects of delays in Malaysian construction industry
  publication-title: International Journal of Project Management
  doi: 10.1016/j.ijproman.2006.11.007
  contributor:
    fullname: Sambasivan
– volume: 18
  start-page: 39
  year: 1981
  ident: 10.1016/j.sbspro.2013.12.407_bib0055
  article-title: Evaluating structural equation models with unobservable variables and measurement error
  publication-title: Journal of Marketing Research
  doi: 10.1177/002224378101800104
  contributor:
    fullname: Fornell
– ident: 10.1016/j.sbspro.2013.12.407_bib0040
– volume: 33
  start-page: 177
  issue: 1
  year: 2009
  ident: 10.1016/j.sbspro.2013.12.407_bib0115
  article-title: Using PLS path modeling for assessing hierarchical construct models: Guidelines and empirical illustration
  publication-title: MIS Quarterly
  doi: 10.2307/20650284
  contributor:
    fullname: Wetzels
– ident: 10.1016/j.sbspro.2013.12.407_bib0045
– ident: 10.1016/j.sbspro.2013.12.407_bib0065
  doi: 10.2753/MTP1069-6679190202
– volume: 17
  start-page: 294
  issue: 2
  year: 2010
  ident: 10.1016/j.sbspro.2013.12.407_bib0075
  article-title: An investigation of the status of the Malaysian construction industry
  publication-title: Benchmarking: An International Journal
  doi: 10.1108/14635771011036357
  contributor:
    fullname: Ibrahim
SSID ssj0000313922
Score 1.9030981
Snippet This paper focused on examining the effect of various factors on budget overrun in construction projects undertaken using management procurement method in...
SourceID crossref
elsevier
SourceType Aggregation Database
Publisher
StartPage 120
SubjectTerms Budget overrun
Management Procurement Method
PLS-SEM
Title Examining Factors Affecting Budget Overrun of Construction Projects Undertaken through Management Procurement Method Using PLS-sem Approach
URI https://dx.doi.org/10.1016/j.sbspro.2013.12.407
Volume 107
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV1LS8QwEA6iFy_iE9cXc_Cgh7CbNk2a47q4iPgCFRYvJWlSUbGKXcH_4J82k6Y-QDx4bJpAySTfDNNv5iNkl5mKGcErKrVJKWcuo7kROa0M05l3mFYoLHA-PRNH1_x4kk1myKirhUFaZcT-FtMDWseRftzN_vPdXf-S5VJixO9ROMPA3uNw6r0zFvFNDj7zLNibUIWfCTif4oKugi7QvBrTeKhCjleKeUGOurK_eahvXme8SBZiuAjD9ouWyIyrl0mvramFeC8b2IvNo_dXyPvhm34Mog8wbqV0YBgoGzhy8Gpv3RTO_fF9ea3hqQLU6-w6yMJFm5VpIIghTfWDqyHq-MAXTQanlTGtCKdBgBoC8QAuTi5p4x5hGPuUr5Lr8eHV6IhGwQVaMh8HUjFQrmQ2ZU5Zl0rpygF32JAusSpVLvPOXTLFjRhwqa30sZg2rBRVklieeZuna2S2fqrdOoEqlWWlTa59-OHf5UZbYZVyibA259b1CO02uXhu-2oUHeHsvmiNUqBRCpYU3ig9IjtLFD_OR-Gh_8-VG_9euUnm8QnJK4xtkVlvDrftQ5Cp2QlnbIfMnY0m5zcfhn3egQ
link.rule.ids 315,783,787,3515,27938,27939,45888
linkProvider Elsevier
linkToHtml http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwnV1NT9wwELVge4ALKqWo28859FAO1q4Tx46PC2K1tLsUCZD2Ztmxg6AiILIr9T_wp_E4Tj8k1EOvdkaKPM7M0-TNPEI-M1szK3hNpbE55cwXtLSipLVlpggJ0wmFDc6LUzG75F-XxXKDHPW9MEirTLG_i-kxWqeVUTrN0f319eiclVIi4g9RuEBgv0leYNsl8rpOloe_Ci04nFDFvwloQNGib6GLPK_WtiFWIckrx8IgR2HZ51LUH2ln-pLsJLwIk-6VdsmGb16RYddUC-nDbOFLmh59sEcej3-a26j6ANNOSwcmkbOBK4drd-VX8D3c34d1A3c1oGBnP0IWzrqyTAtRDWllfvgGkpAP_ObJ4GNVqivCIipQQ2QewNn8nLb-FiZpUPlrcjk9vjia0aS4QCsWgCAVY-Ur5nLmlfO5lL4ac48T6TKncuWLkN0lU9yKMZfGyQDGjGWVqLPM8SI4Pd8ng-au8W8I1LmsamNLE_BH2CutccIp5TPhXMmdHxLaH7K-7wZr6J5xdqM7p2h0imaZDk4ZEtl7Qv91QXSI_f-0fPvflp_I1uxiMdfzk9Nv78g27iCThbH3ZBBc4z8EPLKyH-N9ewLg29_6
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=Examining+Factors+Affecting+Budget+Overrun+of+Construction+Projects+Undertaken+through+Management+Procurement+Method+Using+PLS-sem+Approach&rft.jtitle=Procedia%2C+social+and+behavioral+sciences&rft.au=Rahman%2C+Ismail+Abdul&rft.au=Memon%2C+Aftab+Hameed&rft.au=Karim%2C+Ahmad+Tarmizi+Abd&rft.date=2013-12-11&rft.pub=Elsevier+Ltd&rft.issn=1877-0428&rft.eissn=1877-0428&rft.volume=107&rft.spage=120&rft.epage=128&rft_id=info:doi/10.1016%2Fj.sbspro.2013.12.407&rft.externalDocID=S1877042813050301
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=1877-0428&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=1877-0428&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=1877-0428&client=summon