ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK

Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week sh...

Full description

Saved in:
Bibliographic Details
Published inJurnal ilmiah teknik sipil (Online) Vol. 25; no. 1; pp. 83 - 92
Main Authors Dharmayanti, G.A.P Candra, Putera, I Gusti Agung Adnyana, Prasetya, Made Yoga
Format Journal Article
LanguageEnglish
Indonesian
Published Universitas Udayana 29.01.2021
Online AccessGet full text
ISSN1411-1292
2541-5484
DOI10.24843/JITS.2021.v25.i01.p10

Cover

Abstract Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week showed a 3,76% delay in project implementation. This affects the project completion time and the contractor may be subject to penalty for the delay. This study’s purpose to design a schedule to get the acceleration of construction time using the fast track method and compare the results obtained by the conditions of project implementation experiencing delays. Secondary data used include time schedules, budget plans (RAB), weekly reports of supervisory consultants, analysis of contractor unit prices, and project drawings. The value of the implementation budget plan (RAP) is Rp45.917.529.226,76 calculated based on the RAB of the contractor without taxes and profits. The results of the analysis using the fast track method show that the project can be accelerated so that it can be finished according to the planned schedule by accelerating by 59 days (22,7%) from the duration of project implementation in a late condition (without acceleration). In terms of cost, project implementation in a late condition incurs more costs than the project implementation using the fast track method. The magnitude of the additional costs of implementing the project with a late condition of Rp2.656.202.803,55 or 5,468% more than the application of the fast track method. The application of the fast track method results in changes in the number of workers and material procurement needs at a time caused by the time shifts in activities implemented out in parallel.
AbstractList Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began work on May 6, 2019, and planned to finish on December 1, 2019. At the time of the study, the project progress report up to the 12th week showed a 3,76% delay in project implementation. This affects the project completion time and the contractor may be subject to penalty for the delay. This study’s purpose to design a schedule to get the acceleration of construction time using the fast track method and compare the results obtained by the conditions of project implementation experiencing delays. Secondary data used include time schedules, budget plans (RAB), weekly reports of supervisory consultants, analysis of contractor unit prices, and project drawings. The value of the implementation budget plan (RAP) is Rp45.917.529.226,76 calculated based on the RAB of the contractor without taxes and profits. The results of the analysis using the fast track method show that the project can be accelerated so that it can be finished according to the planned schedule by accelerating by 59 days (22,7%) from the duration of project implementation in a late condition (without acceleration). In terms of cost, project implementation in a late condition incurs more costs than the project implementation using the fast track method. The magnitude of the additional costs of implementing the project with a late condition of Rp2.656.202.803,55 or 5,468% more than the application of the fast track method. The application of the fast track method results in changes in the number of workers and material procurement needs at a time caused by the time shifts in activities implemented out in parallel.
Author Prasetya, Made Yoga
Dharmayanti, G.A.P Candra
Putera, I Gusti Agung Adnyana
Author_xml – sequence: 1
  givenname: G.A.P Candra
  surname: Dharmayanti
  fullname: Dharmayanti, G.A.P Candra
– sequence: 2
  givenname: I Gusti Agung Adnyana
  surname: Putera
  fullname: Putera, I Gusti Agung Adnyana
– sequence: 3
  givenname: Made Yoga
  surname: Prasetya
  fullname: Prasetya, Made Yoga
BookMark eNo9kd9OgzAUhxujiXPuFUxfAOwpBcZlHXUijC3ALnbVlNIajIoBY-Lb223Gq_PL-fNdnO8GXX4MHwahOyA-ZUsW3D9nTe1TQsH_pqHfE_A_gVygGQ0ZeKFbuUQzYAAe0IReo8U09S1hLGZxnLAZeuclL7I6q_FOVCux4w0vXSx4XrvJMVfbg8jxvswaXPCDa5Y452UuKtyIasfTPa7qfYofHAZveJnyiuNUlGu3txHNNhX4kdcNbiq-ym_RlVVvk1n81TnaP4pm9eQV23W24oWnIQLiBQmjxDITa51AtFQAQdu1Om7BGGWUJXFkbcc6oolh7qDTMVHaBppFLDA2CeYoO3O7Qb3Kz7F_V-OPHFQvT41hfJFq_Or1m5HLICSKGZWEnXsTSVzt2mhpDdCWJW3rWNGZpcdhmkZj_3lA5MmBPDqQRwfSOZDOgXQOgl91u3Rv
ContentType Journal Article
DBID AAYXX
CITATION
DOA
DOI 10.24843/JITS.2021.v25.i01.p10
DatabaseName CrossRef
DOAJ Directory of Open Access Journals
DatabaseTitle CrossRef
DatabaseTitleList CrossRef

Database_xml – sequence: 1
  dbid: DOA
  name: DOAJ Directory of Open Access Journals
  url: https://www.doaj.org/
  sourceTypes: Open Website
DeliveryMethod fulltext_linktorsrc
Discipline Engineering
EISSN 2541-5484
EndPage 92
ExternalDocumentID oai_doaj_org_article_8350a4ea95d1410995ddb68fe12b49bb
10_24843_JITS_2021_v25_i01_p10
GroupedDBID AAYXX
ADBBV
ALMA_UNASSIGNED_HOLDINGS
BCNDV
CITATION
GROUPED_DOAJ
ID FETCH-LOGICAL-c1610-39420f4e7cc9168a113bdbc7b1eeaeaf076ffd4d0c0e4610dc70acf3c4643ef93
IEDL.DBID DOA
ISSN 1411-1292
IngestDate Wed Aug 27 01:26:05 EDT 2025
Tue Jul 01 04:15:48 EDT 2025
IsDoiOpenAccess true
IsOpenAccess true
IsPeerReviewed true
IsScholarly true
Issue 1
Language English
Indonesian
LinkModel DirectLink
MergedId FETCHMERGED-LOGICAL-c1610-39420f4e7cc9168a113bdbc7b1eeaeaf076ffd4d0c0e4610dc70acf3c4643ef93
OpenAccessLink https://doaj.org/article/8350a4ea95d1410995ddb68fe12b49bb
PageCount 10
ParticipantIDs doaj_primary_oai_doaj_org_article_8350a4ea95d1410995ddb68fe12b49bb
crossref_primary_10_24843_JITS_2021_v25_i01_p10
ProviderPackageCode CITATION
AAYXX
PublicationCentury 2000
PublicationDate 2021-01-29
PublicationDateYYYYMMDD 2021-01-29
PublicationDate_xml – month: 01
  year: 2021
  text: 2021-01-29
  day: 29
PublicationDecade 2020
PublicationTitle Jurnal ilmiah teknik sipil (Online)
PublicationYear 2021
Publisher Universitas Udayana
Publisher_xml – name: Universitas Udayana
SSID ssib044747794
ssj0002875764
Score 2.1340384
Snippet Unit Layanan Kanker Terpadu RSUD Bali Mandara construction project has a building area of 4.272,74 m2. Projects with a contract value of Rp52.364.056.071 began...
SourceID doaj
crossref
SourceType Open Website
Index Database
StartPage 83
Title ANALISIS PERCEPATAN PELAKSANAAN PROYEK UNIT LAYANAN KANKER TERPADU RSUD BALI MANDARA DENGAN METODE FAST TRACK
URI https://doaj.org/article/8350a4ea95d1410995ddb68fe12b49bb
Volume 25
hasFullText 1
inHoldings 1
isFullTextHit
isPrint
link http://utb.summon.serialssolutions.com/2.0.0/link/0/eLvHCXMwrV1Lb9QwELZQT3BAPEWBVj5wTddxnIeP7sbbbrObrpKs1J4sP6UiURAqHPntjJNtlRsXLonlWCPry2j8jT2eQegLpRZsYLBJyAqWsMKUCafaJMFVNqeVLdlYOmHbFpd7dnWT38xKfcWYsCk98ATcAhgC0cxrnrsYksjh7UxRBZ9Sw7gx0foSTmbOFGgSY8CSHzXt67iFVAKxHo-YWYzhopxO14Upq1i2uFoPPfiKND37TfOzOwLmK16pna1Us4T-48qzeoVeHigjFtNUX6Nnd-4NejFLJPgWfROt2Kz7dY93slvKnRhEC82NaHr4Etvd9a1sMHh7A96IW-hscSPaRnYY-OxO1Hvc9fsan4MYvBVtLTqBa9lewLitHK5riVeiH_DQiWXzDu1XclheJodCCokFQgd2ljNKAvOltcAGK52mmXHGlib1XnsdSFmE4JgjlviYf93ZkmgbMsuAr_jAs_fo6P77vf-AMGex2pGG3-gMI7o02gKgwNGc4yAsP0aLR9DUjylfhgI_Y4RZRZhVhFkBzApgVgDzMTqP2D6Njvmuxw7QAnXQAvUvLfj4P4R8Qs_j5OIGC-Wf0dHDz1_-BCjHgzkdtQue2z_yL9Emx5g
linkProvider Directory of Open Access Journals
openUrl ctx_ver=Z39.88-2004&ctx_enc=info%3Aofi%2Fenc%3AUTF-8&rfr_id=info%3Asid%2Fsummon.serialssolutions.com&rft_val_fmt=info%3Aofi%2Ffmt%3Akev%3Amtx%3Ajournal&rft.genre=article&rft.atitle=ANALISIS+PERCEPATAN+PELAKSANAAN+PROYEK+UNIT+LAYANAN+KANKER+TERPADU+RSUD+BALI+MANDARA+DENGAN+METODE+FAST+TRACK&rft.jtitle=Jurnal+ilmiah+teknik+sipil+%28Online%29&rft.au=G.A.P+Candra+Dharmayanti&rft.au=I+Gusti+Agung+Adnyana+Putera&rft.au=Made+Yoga+Prasetya&rft.date=2021-01-29&rft.pub=Universitas+Udayana&rft.issn=1411-1292&rft.eissn=2541-5484&rft.volume=25&rft.issue=1&rft.spage=83&rft.epage=92&rft_id=info:doi/10.24843%2FJITS.2021.v25.i01.p10&rft.externalDBID=DOA&rft.externalDocID=oai_doaj_org_article_8350a4ea95d1410995ddb68fe12b49bb
thumbnail_l http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/lc.gif&issn=1411-1292&client=summon
thumbnail_m http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/mc.gif&issn=1411-1292&client=summon
thumbnail_s http://covers-cdn.summon.serialssolutions.com/index.aspx?isbn=/sc.gif&issn=1411-1292&client=summon