A Hybrid Multiobjective Genetic Algorithm for Robust Resource-Constrained Project Scheduling with Stochastic Durations

We study resource-constrained project scheduling problems withperturbation on activity durations. With the consideration of robustnessand stability of a schedule, we model the problem as a multiobjective optimizationproblem. Three objectives—makespan minimization, robustnessmaximization, and stabili...